1. Flow and WIP

Every job follows the same general flow through the shop between its release onto the floor and its shipment to the customer. At any moment every job in WIP sits somewhere in this flow, and its lead time, the working days from release to shipment, is the time it takes to pass through it.

Job Flow, Release to Shipment
Job Flow, Release to Shipment

In 2025, the shop carried an average of 238 WIP jobs against a throughput of about 19 shipped a day, so a job spent about 12 working days on the floor. 2025 WIP was skewed by the large Q1 backlog detailed below. WIP averaged 187 jobs over the past three years and peaks every December: 260 jobs in 2023, 466 in 2024 and 418 in 2025.

Average WIP and Working Days on the Floor, 2023 to 2025
Average WIP and Working Days on the Floor, 2023 to 2025

WIP peaked at 466 jobs at the end of 2024 against a Q3 2024 average of 150. In Q4 2024, the shop released 26% more brake standard hours than in Q3. This surge pushed the lasers to 92% of scheduled hours on average over the six weeks from November 18, vs. 69% in Q3. Over those weeks, 96 to 223 jobs were waiting to be cut, vs. an average of 35 jobs in Q3. The work then queued at the brakes, which already run at 90% in a normal quarter, and it took through Q1 and into Q2 2025 to clear this backlog. See Appendix Table 1 for additional detail.

Weekly WIP and Net Inflow, Q3 2024 to Q2 2025
Weekly WIP and net inflow, July 2024 to June 2025

By location, the brakes (queue, setup and run together) hold 28% of WIP in 2025, while the laser cutting stations hold 22% and outside processing 10%. The other eight work centers and jobs complete but not yet shipped hold the remaining 40% between them, none above 9%. In Q2-Q4 the brakes' share falls to 17% and the lasers' rises to 24%, as a result of the Q1 backlog having been worked through.

Average Share of Jobs in WIP by Location
WIP by location

The 2025 average floor WIP of 238 jobs was 0.96x the WIP the quoted lead times imply at measured throughput; in Q2-Q4 it was 202 WIP jobs against 240 implied (0.84x). The excess for the year is a result of the first-quarter backlog. In Q2-Q4 the floor carried 38 fewer jobs than its quoted lead times allow at the throughput it achieved, so it could have taken on about 19% more work, or quoted shorter lead times, and still shipped the average job inside its quote. See Appendix Table 2 for additional detail.

2. Lead Time

Lead time decomposition

In 2025, the average lead time of all jobs was 12.8 days, and in Q2-Q4 it was 10.3 days. 84% of lead time in 2025 was spent waiting (movement between and queueing at work centers), against 6% spent working at machines (both setup and run), and 10% with outside vendors. The time spent waiting was concentrated: in 2025, the brake queue alone was 3.1 days of the average job's lead time (24% of total), and the brakes held 53% of all queue time. The brake queue time in 2025 was highly skewed: the median queue time was 1.0 day, with a 90th percentile of 9.5 days. We've presented Q2-Q4 data alongside 2025, as this largely removes the impact of the Q4 build and presents a more normalized view. See Appendix Table 3 for additional detail.

Lead Time Decomposition by Stage, 2025 and Q2-Q4
Lead Time Decomposition by Stage, 2025 and Q2-Q4

Actual vs. quoted lead times

In 2025, the median job shipped in 11.2 working days vs. an average quoted lead time of 12.9; in Q2-Q4, it was 9.2 vs. 12.5. The quoted lead time was met on 63% of jobs in 2025 and 77% in Q2-Q4. The quote was met on 59% of repeat-part jobs in 2025 (72% in Q2-Q4), 73% of new-part jobs (88%) and 72% of outside-processing jobs (90%). See Appendix Table 4 for additional detail.

The shop quotes lead times by starting with a routing class standard (10 working days for repeat parts, 15 for new parts and 20 with outside processing) which is then adjusted slightly based on current shop capacity and WIP levels. Section 4 analyzes the quote against the brake backlog.

Actual vs. Quoted Lead Times, by Routing Class
Lead time distribution by routing class

3. On-time and Late Jobs

A job's due date is set as the later of the quote and the customer's requested date. Requested dates were 74% of job due dates in 2025, with a median of 15 working days. On-time delivery was 81% in 2025, and in Q2-Q4 once the backlog was worked through, on-time delivery was 91%.

There were 987 late jobs in 2025, with a median days late of 3 and a 90th percentile of 7. That dropped to 323 late jobs in Q2-Q4, with a median days late of 2 and a 90th percentile of 7. In 2025, 40% of jobs shipped 6 days or more before the due date. See Appendix Tables 5 and 6 for additional detail.

Working Days Shipped After the Due Date, 2025 and Q2-Q4
Working Days Shipped After the Due Date, 2025 and Q2-Q4

Late job lead time decomposition

In 2025, the brake queue was 24% of all jobs' lead time and accounted for the largest share of the extra days on late jobs: 5.76 days against 2.50 for on-time jobs. This was due to the first quarter's backlog: the 2024 year-end build released more work than the brakes could absorb and put 664 of the year's 987 late jobs into Q1. In Q2-Q4, with the backlog cleared, late jobs waited less at the brakes than on-time jobs (0.73 days against 1.54).

In Q2-Q4, the extra days on late jobs were due to material wait at the first operation (2.35 days for late jobs vs. 0.65 for on-time jobs), outside processing (2.24 vs. 1.17), the robotic weld queue (1.14 vs. 0.17) and setup and run (1.81 vs. 0.66; the average lot size for late jobs was 72 pieces vs. 47 for on-time jobs). See Appendix Tables 7a and 7b for additional detail.

Lead time by stage, on-time vs. late jobs
Lead time by stage, on-time and late jobs

Drivers behind late jobs

We analyzed the ERP and shop-floor records to arrive at an attribution of lost days (i.e., how many days late the jobs shipped) by driver. For each late job, we considered how many days it ran longer than an on-time job of the same routing class at each stage, as well as material holds and late purchase order receipts. We then assigned each job to a driver.

In 2025, jobs waiting at work centers (i.e., queue constraints) accounted for 42% of the 3,473 lost days, while jobs that were released late accounted for 21%, and jobs that waited on material and outside processing accounted for 7% and 3%, respectively. In Q2-Q4, jobs that were released late accounted for 48% of the 1,035 lost days, with queue constraint (16%), material (12%) and outside processing (3%) the other main drivers. Jobs were released late when they went to the floor with fewer working days to the due date than the job's quoted lead time; this was the largest driver on 162 of the 323 (50%) late jobs in Q2-Q4. See Appendix Tables 8, 9a and 9b for additional detail.

Lost days by attributed driver
Lost days by attributed driver

The chart below shows where on the floor the lost days were incurred: each work center's lost days in 2025 and in Q2-Q4, split by attributed driver. It excludes the days attributed to jobs released late (732 of the 3,473 lost days in 2025 and 501 of the 1,035 in Q2-Q4), since those days are lost at order entry, before the job reaches a work center.

Lost days by work center and attributed driver
Lost days by work center and attributed driver

24% of lost days in 2025 and 18% in Q2-Q4 have no attribution. Of the 823 non-attributed lost days in 2025, 27% was from work center queue time above on-time median but below the attribution threshold, 30% from setup and run time above normal with no overrun or rework recorded, and 16% from movement between stages. The remainder have no single discernible driver. See Appendix Tables 10 and 11 for additional detail.

The shop's own records

Late-reason codes are inputted retroactively on late jobs by the customer service team during the weekly delivery review. These codes are pulled from a dropdown list with six choices: capacity, material, outside processing, customer change, quality and other. As seen below, a significant portion of late jobs had no late-reason code entered (36% in 2025 and 37% in Q2-Q4). See Appendix Table 12 for additional detail.

Late-reason codes as entered on late jobs
Late-reason codes as entered on late jobs

To validate the accuracy of these codes, we compared them against the lost days attribution drivers shown above. We first mapped the late-reason codes to the corresponding attribution drivers: queue constraint and setup overrun count as capacity; material, outside processing and quality as their own codes; a hold and days not attributed as other. The notable exception is that the "released late" attribution driver is not a listed option for late-reason codes; those jobs are mostly coded as capacity or other (112 of the 149 with a code), and count as other in the comparison. We recommend adding this late-reason code into the system, given it accounts for a significant portion of lost days.

As shown below, the shop's entered reason-codes do not adequately capture the true drivers of lost days. The entered code agrees with the largest attributed cause on just 43.9% of coded late jobs against the 35.9% expected had the codes been assigned at random (34.7% against 25.1% in Q2-Q4). Queue constraint is the largest attributed driver on just 54% of the jobs coded capacity, while being misattributed across the rest (making up 50% of the jobs with no code and 19-76% of the other drivers). Material is the largest cause on just 21 of the 78 (27%) jobs coded material, outside processing on none of the 37 coded outside processing (0%) and quality on none of the 27 (0%) coded quality. Of the 241 jobs where released late is the largest attributed driver, 72 are coded capacity, 92 carry no code and 40 are coded other. See Appendix Tables 13 and 14 for additional detail.

What the shop coded against what the data shows
What the shop coded against what the data shows

To increase the accuracy and usefulness of its late-reason codes, the shop should consider process changes to (i) include additional options (specifically late releases) in the late-reason code dropdown menu, and (ii) enable real-time shop-floor data capture on the reasons for late jobs once they're known.

4. Quoting

The shop's quoted lead time was off by 4.8 days on average from 2023 to 2025. The current practice of quoting standard lead times based on the part's routing class, and then adjusting this higher during periods of low capacity, proved to be inaccurate in both directions.

First, the fixed standards were consistently too high: in months of normal capacity, the shop over-estimated lead times by an average of 2.5 days. Second, during the period in Q4 2024 to Q1 2025 when the shop's capacity was constrained and lead times increased, the shop's lead time adjustments arrived too late and were too low in quantity, and so under-estimated lead times by 5.8 days in the four months from December 2024 to March 2025. See Appendix Table 15 for additional detail.

Quoted and Actual Lead Time by Release Month, Non-rush Jobs, 2023 to 2025
Quoted and Actual Lead Time by Release Month, Non-rush Jobs, 2023 to 2025

Brake backlog at release explains 23% of the lead time quoting error. The quote runs 3.1 days long below 1 day of backlog and 5.6 to 6.2 days short above 3. Outside processing quotes run 4.2 days long: the median job takes 14 days against the 20-day standard. Job size and lot size explain under 1%. The backlog at release sees a build late: jobs released in November 2024 ran 3.5 days over their quotes at 1.4 days of backlog. See Appendix Table 16 for additional detail.

Recommendation

The recommended quote is the median lead time of jobs of the same routing class at the same brake backlog at release, refitted monthly from the jobs shipped; the table below gives it as fitted on 2023 to 2025. Fitted that way, it misses by 3.2 days in ordinary months and 5.6 in the build, against 4.4 and 7.3 for today's quote, and quotes shorter than today on 84% of jobs, by 3.9 days on average, and longer on 14%, by 3.6. Applied month by month as the shop would have had it at the time, it does as well in ordinary months (3.4 days) but not in the 2024 build (8.9), because no earlier job had shipped from a backlog above 3 days. A median quote is met by about half of jobs; at the 80th percentile of the same cell the commitment is met on 82% of jobs, against 72% for today's quote. See Appendix Tables 17, 18 and 19 for additional detail.

Quoted Lead Time by Routing Class and Brake Backlog at Release, Working Days, Fitted on 2023 to 2025
Routing classClass standardClass medianUnder 1 day1 to 2 days2 to 3 days3 to 5 daysOver 5 days
Repeat part10878111618
New part159810152122
Outside processing20141314202926
Mean Absolute Error of the Quote by Release Month, Current Quote Against the Recommended Quote, 2023 to 2025
Mean Absolute Error of the Quote by Release Month, Current Quote Against the Recommended Quote, 2023 to 2025
Quote Error in Ordinary and Loaded Months, Current Quote Against Each Candidate
Quote Error in Ordinary and Loaded Months, Current Quote Against Each Candidate

Appendix

Table 1. Year-end WIP build by year

YearThird-quarter mean WIPDecember peak WIPPeak datePeak over third-quarter meanOn time, following first quarterMedian lead time, following first quarter
2023126260Dec 222.193.2%8.2
2024150466Dec 233.152.4%19.2
2025189418Dec 232.2

Table 2. Floor WIP against the WIP the quoted lead times imply

PeriodWorking daysJobs shippedMean WIPJobs shipped per dayMean quoted lead timeWIP at quoted lead timesRatioWIP over throughput (days)Mean days in WIPMean lead time
20252665,12923819.2812.902490.9612.3512.5712.78
2025 Q2-Q41943,73420219.2512.482400.8410.5210.0810.29

Table 3. Queue time by work center

Work centerOperationsQueue daysShareMeanMedian90th percentileShare, Q2-Q4Mean, Q2-Q4Median, Q2-Q490th percentile, Q2-Q4
Press brake5,56617,01353.2%3.061.029.5135.3%1.480.554.13
Grind and deburr5,5724,90215.3%0.880.801.8721.4%0.890.811.88
Inspection and pack5,1293,52611.0%0.690.791.0716.1%0.740.821.06
Hardware2,1181,7485.5%0.830.711.707.6%0.840.721.63
Manual weld1,5331,3284.1%0.870.721.815.0%0.760.731.44
Robotic weld4201,2073.8%2.871.197.945.7%3.211.279.09
Powder coat2,3281,1633.6%0.500.101.904.3%0.430.091.70
Assembly6841,1153.5%1.630.864.014.6%1.530.853.76

Table 4. Lead time against the quoted lead time by routing class

PeriodRouting classJobsQuotedMedianMean90th percentileWithin quotedOn timeLate jobsMedian, on timeMedian, late
2025All5,12912.911.212.823.263.0%80.8%9879.219.2
2025Repeat part3,69810.69.211.421.259.2%82.2%6598.217.2
2025New part46215.511.212.823.273.4%82.5%8110.222.2
2025Outside processing96920.516.218.230.272.4%74.5%24714.227.2
2025 Q2-Q4All3,73412.59.210.317.276.8%91.3%3239.213.2
2025 Q2-Q4Repeat part2,67810.18.29.015.271.8%91.9%2187.212.2
2025 Q2-Q4New part34615.110.210.516.788.4%93.1%2410.216.7
2025 Q2-Q4Outside processing71020.114.215.221.289.7%88.6%8114.222.2

Table 5. On-time delivery and lead time by quarter shipped

Quarter shippedJobs shippedLate jobsOn timeMedian lead time90th percentile
2023 Q11,1888792.7%9.222.2
2023 Q21,0425494.8%7.213.2
2023 Q39816993.0%7.214.2
2023 Q41,1319092.0%8.216.2
2024 Q11,2168393.2%8.216.2
2024 Q21,1066594.1%7.214.2
2024 Q31,0608192.4%8.216.2
2024 Q41,17114287.9%9.218.2
2025 Q11,39566452.4%19.231.2
2025 Q21,3158193.8%9.217.2
2025 Q31,18611890.1%9.217.2
2025 Q41,23312489.9%9.217.2

Table 6. Jobs shipped by working days from the due date to the ship date, 2025 and Q2-Q4

Working days from the due date to the ship dateJobs shipped, 2025Jobs shipped, 2025 Q2-Q4
10 or more early802763
9 early227222
8 early287269
7 early350321
6 early390348
5 early395351
4 early367324
3 early341273
2 early362249
1 early322163
on the due date299128
1 late26697
2 late20172
3 late13552
4 late10831
5 late7922
6 late6314
7 late438
8 late3110
9 late245
10 or more late3712
All jobs5,1293,734

Table 7a. Lead time by stage, 2025: mean working days per job, stages in routing order

StageAll jobsShare of lead timeOn timeLate
Release to traveler print0.907.1%0.890.97
First-operation queue1.4811.6%1.083.16
Material wait at first operation0.856.6%0.681.55
Queue: press brake3.1324.5%2.505.76
Queue: hardware0.221.7%0.230.18
Queue: manual weld0.191.5%0.180.21
Queue: robotic weld0.231.8%0.150.58
Queue: grind and deburr0.665.2%0.680.58
Powder scheduling wait0.463.6%0.400.73
Queue: powder coat0.161.3%0.130.33
Queue: assembly0.201.6%0.120.54
Queue: inspection and pack0.514.0%0.590.19
Setup and run0.826.4%0.671.47
Move0.796.2%0.741.03
Hold: customer0.090.7%0.080.13
Hold: engineering0.060.5%0.050.09
Hold: material0.010.0%0.000.01
Hold: other0.030.2%0.030.03
Hold: quality0.040.3%0.030.06
Hold: tooling0.030.2%0.030.04
Outside processing1.279.9%1.101.96
Packed, waiting to ship0.675.3%0.630.84
Lead time, mean12.7810.9720.38
Lead time, median11.29.219.2
Jobs5,1294,142987

Table 7b. Lead time by stage, 2025 Q2-Q4: mean working days per job, stages in routing order

StageAll jobsShare of lead timeOn timeLate
Release to traveler print0.878.5%0.870.86
First-operation queue0.838.1%0.850.62
Material wait at first operation0.807.8%0.652.35
Queue: press brake1.4714.3%1.540.73
Queue: hardware0.232.2%0.230.18
Queue: manual weld0.161.5%0.160.14
Queue: robotic weld0.252.4%0.171.14
Queue: grind and deburr0.686.6%0.700.45
Powder scheduling wait0.444.3%0.410.74
Queue: powder coat0.131.3%0.130.18
Queue: assembly0.191.8%0.140.74
Queue: inspection and pack0.565.5%0.610.08
Setup and run0.767.4%0.661.81
Move0.787.6%0.751.20
Hold: customer0.080.8%0.080.13
Hold: engineering0.060.6%0.060.11
Hold: material0.010.1%0.010.02
Hold: other0.030.3%0.030.05
Hold: quality0.040.4%0.040.06
Hold: tooling0.030.3%0.030.04
Outside processing1.2612.3%1.172.24
Packed, waiting to ship0.656.3%0.630.91
Lead time, mean10.299.8714.74
Lead time, median9.29.213.2
Jobs3,7343,411323

Table 8. Lost days of late jobs by attributed cause, 2025 and Q2-Q4

CauseLost days, 2025ShareLate jobs with the causeJobs where largestLost days, Q2-Q4Share, Q2-Q4Late jobs with the cause, Q2-Q4Jobs where largest, Q2-Q4
Queue constraint1,46642.2%68749916415.9%13062
Released late73221.1%25224150148.4%166162
Material2416.9%2168412612.2%10351
Outside processing1012.9%6410272.6%256
Setup overrun120.3%28120.1%50
Quality471.4%833161.6%241
Hold521.5%1020111.0%200
Not attributed82323.7%78414918818.2%19341
Total3,473100.0%9879871,035100.0%323323

Table 9a. Lost days by work center and cause, 2025

Work centerLost daysShareQueue constraintReleased lateMaterialOutside processingSetup overrunQualityHoldNot attributed
Laser88125.4%538019001810134
Order entry (promise)73221.1%0732000000
Press brake63818.4%4500004810166
Assembly1915.5%13100013056
Robotic weld1614.6%11600022141
Grind and deburr1414.0%43000011186
Punch1363.9%53049010132
Outside processing1323.8%00010101326
Manual weld1243.6%21000116086
Powder coat1002.9%7900000615
Shipping962.8%000000096
Hardware742.1%2101004444
Inspection and pack681.9%1300004742

Table 9b. Lost days by work center and cause, 2025 Q2-Q4

Work centerLost daysShareQueue constraintReleased lateMaterialOutside processingSetup overrunQualityHoldNot attributed
Order entry (promise)50148.4%0501000000
Laser13513.1%110106004212
Robotic weld868.3%6300000022
Assembly504.9%3300000017
Press brake454.3%2300011020
Manual weld434.2%400007031
Punch413.9%1402000015
Grind and deburr353.4%400000426
Outside processing343.3%000270007
Shipping232.2%000000023
Hardware181.7%300001113
Powder coat131.3%90000004
Inspection and pack111.0%00000118

Table 10. Stage composition of the lost days not attributed

StageDays not attributed, 2025ShareDays not attributed, Q2-Q4Share, Q2-Q4
Setup and run24830.1%9249.0%
Move13216.0%3518.8%
Queue: press brake10813.2%21.0%
Packed, waiting to ship9611.7%2312.1%
Material wait at first operation617.4%31.3%
First-operation queue364.3%10.3%
Release to traveler print313.8%10.6%
Outside processing263.2%63.4%
Queue: robotic weld202.5%126.6%
Queue: hardware172.0%52.4%
Queue: assembly141.7%10.7%
Queue: grind and deburr141.7%21.0%
Queue: manual weld91.1%31.6%
Hold: other60.8%21.1%
Queue: inspection and pack30.3%00.0%
Queue: powder coat10.1%00.0%
Total823100.0%188100.0%

Table 11. Queue constraint and not attributed shares by queue threshold

Queue threshold of the constraint ruleQueue constraint, 2025Not attributed, 2025Queue constraint, Q2-Q4Not attributed, Q2-Q4
70th percentile (the rule)42.2%23.7%15.9%18.2%
80th percentile34.9%31.0%13.4%20.7%
90th percentile21.4%44.5%9.4%24.6%

Table 12. Late-reason codes by period shipped

Period shippedLate jobsBlankCapacity share of entered codes
202330039.0%48.1%
202437133.4%59.5%
202598736.4%60.5%
2025 Q2-Q432337.5%55.0%

Table 13. Agreement of the entered code with the largest attributed cause

ComparisonPeriodLate jobsCode agrees with largest attributed causeChance levelOver chance
All coded late jobs202562843.9%35.9%+8.0 points
All coded late jobs2025 Q2-Q420234.7%25.1%+9.5 points
Jobs whose largest cause has a code202538359.0%54.7%+4.3 points
Jobs whose largest cause has a code2025 Q2-Q47548.0%44.1%+3.9 points

Table 14. Entered code against largest attributed cause, 2025

Code enteredQueue constraintReleased lateMaterialOutside processingSetup overrunQualityHoldNot attributed
Capacity2047230412067
Material34162110006
Outside processing2110100005
Customer change323200005
Quality158100003
Other12402000010
Blank1819227501053

Table 15. The current quote against actual lead time by period and routing class, non-rush jobs released 2023 to 2025

Period, by release dateRouting classJobsMean actual lead timeMean quoted lead timeMean errorMean absolute errorWithin 2 daysMean brake backlog at release
2023 to 2025All10,99611.1312.64-1.514.7827.8%1.27
2023 to 2025Repeat part7,8369.7910.22-0.434.2032.4%1.29
2023 to 2025New part97611.0215.18-4.156.1315.6%1.20
2023 to 2025Outside processing2,18415.9720.16-4.206.2717.1%1.25
2023All3,4589.1912.50-3.314.6326.0%0.55
2023Repeat part2,4387.8810.00-2.123.8031.4%0.55
2023New part3128.6515.00-6.356.799.9%0.54
2023Outside processing70813.9320.00-6.076.5314.7%0.54
2024All3,81711.3812.48-1.105.2026.1%0.96
2024Repeat part2,7089.9710.02-0.054.6230.5%0.96
2024New part33811.5615.00-3.446.5015.1%0.97
2024Outside processing77116.2720.02-3.756.6915.7%0.96
2025All3,72112.6612.92-0.264.5031.3%2.27
2025Repeat part2,69011.3410.62+0.714.1535.2%2.29
2025New part32612.7415.54-2.805.1121.5%2.06
2025Outside processing70517.6820.49-2.815.5521.1%2.28
2025 Q2-Q4All2,79310.7312.38-1.654.0133.7%1.17
2025 Q2-Q4Repeat part2,0019.4410.01-0.573.5138.4%1.16
2025 Q2-Q4New part26010.9415.02-4.085.0021.5%1.16
2025 Q2-Q4Outside processing53215.4620.00-4.545.4222.0%1.19
Loaded monthsAll1,32219.7813.95+5.847.3419.5%4.77
Loaded monthsRepeat part97117.9511.76+6.197.3921.2%4.78
Loaded monthsNew part10621.1016.60+4.506.5617.0%4.57
Loaded monthsOutside processing24526.4721.47+5.007.4713.9%4.81
Ordinary monthsAll9,6749.9412.46-2.514.4429.0%0.80
Ordinary monthsRepeat part6,8658.6310.00-1.373.7533.9%0.80
Ordinary monthsNew part8709.8015.01-5.216.0815.4%0.79
Ordinary monthsOutside processing1,93914.6420.00-5.366.1217.5%0.80

10,996 non-rush jobs released from January 2023 and shipped by December 2025. Left out: 254 released before January 2023, which the record holds only where they shipped late, and 834 lines customer service accepted inside the quote. Error is the actual lead time less the quoted lead time in whole working days; a loaded month has a mean brake backlog at release of 2.5 days or more.

Table 16. Quote error by condition at release, non-rush jobs released 2023 to 2025

Each condition alone

Condition at releaseVariance in quote error explained aloneMean error, lowest bandMean error, highest band
Brake backlog at release (days)22.9%-3.10 (under 1)+5.65 (over 5)
Brake standard hours on the job (quartiles)0.6%-1.94 ((0.524, 1.001])-0.79 ((2.845, 71.245])
Lot size (quartiles)0.4%-1.77 ((0.999, 11.0])-0.85 ((56.0, 500.0])
Operations on the routing1.8%-2.66 (3)-0.19 (8)
Outside processing on the routing5.2%-0.85 (no)-4.20 (yes)
Release month of the year14.7%+1.49 (1)+4.60 (12)

Brake backlog at release (days)

BandJobsMean actual lead timeMean quoted lead timeMean errorMean absolute error
under 16,6559.3412.44-3.104.56
1 to 22,55710.8912.50-1.614.09
2 to 379515.5112.50+3.016.10
3 to 535419.6513.49+6.168.12
over 563520.6114.96+5.656.46

Brake standard hours on the job (quartiles)

BandJobsMean actual lead timeMean quoted lead timeMean errorMean absolute error
(0.524, 1.001]2,74910.8212.75-1.944.84
(1.001, 1.578]2,74911.0012.74-1.744.88
(1.578, 2.845]2,74910.8812.45-1.574.77
(2.845, 71.245]2,74911.8112.60-0.794.65

Lot size (quartiles)

BandJobsMean actual lead timeMean quoted lead timeMean errorMean absolute error
(0.999, 11.0]2,86410.8912.67-1.774.80
(11.0, 25.0]2,75710.8812.60-1.724.81
(25.0, 56.0]2,63510.9012.60-1.694.81
(56.0, 500.0]2,74011.8312.68-0.854.72

Operations on the routing

BandJobsMean actual lead timeMean quoted lead timeMean errorMean absolute error
32788.1710.83-2.665.88
41,3679.1011.80-2.715.18
53,68210.2412.26-2.024.84
62,63511.4612.67-1.214.67
71,88212.3013.01-0.704.47
81,15214.3914.58-0.194.66

Outside processing on the routing

BandJobsMean actual lead timeMean quoted lead timeMean errorMean absolute error
no8,8129.9210.77-0.854.42
yes2,18415.9720.16-4.206.27

Release month of the year

BandJobsMean actual lead timeMean quoted lead timeMean errorMean absolute error
183514.7113.22+1.495.07
287912.9813.61-0.645.47
38899.9513.07-3.124.61
49339.1012.41-3.314.48
59379.3612.51-3.144.30
69909.9212.51-2.594.23
78178.9312.31-3.384.67
884310.2812.15-1.864.30
998910.4412.49-2.054.23
101,0879.4012.50-3.104.42
111,01312.7012.51+0.194.85
1278417.0212.42+4.607.32

Table 17. Every quote tested: error by period, change from the current quote, and how each quote was reached

Error by period

QuotePeriod, by release dateJobsMean errorMean absolute errorWithin 2 daysMean quote
Current quote2023 to 202510,996-1.514.7827.8%12.64
Current quote20233,458-3.314.6326.0%12.50
Current quote20243,817-1.105.2026.1%12.48
Current quote20253,721-0.264.5031.3%12.92
Current quote2025 Q2-Q42,793-1.654.0133.7%12.38
Current quoteLoaded months1,322+5.847.3419.5%13.95
Current quoteOrdinary months9,674-2.514.4429.0%12.46
Class median2023 to 202510,996+2.454.2946.2%8.67
Class median20233,458+0.533.1750.8%8.66
Class median20243,817+3.094.6047.5%8.29
Class median20253,721+3.585.0340.5%9.08
Class median2025 Q2-Q42,793+1.493.3449.2%9.24
Class medianLoaded months1,322+11.3111.4911.0%8.48
Class medianOrdinary months9,674+1.243.3151.0%8.70
Class and brake backlog, out of sample2023 to 202510,996+1.864.0247.7%9.26
Class and brake backlog, out of sample20233,458+0.973.1753.6%8.22
Class and brake backlog, out of sample20243,817+2.924.3648.6%8.46
Class and brake backlog, out of sample20253,721+1.614.4841.3%11.05
Class and brake backlog, out of sample2025 Q2-Q42,793+1.383.5747.5%9.35
Class and brake backlog, out of sampleLoaded months1,322+5.488.9417.8%14.31
Class and brake backlog, out of sampleOrdinary months9,674+1.373.3551.8%8.57
Class and brake backlog, fitted on 2023 to 20252023 to 202510,996+1.233.4849.6%9.90
Class and brake backlog, fitted on 2023 to 202520233,458+0.652.9253.2%8.54
Class and brake backlog, fitted on 2023 to 202520243,817+1.893.7550.2%9.49
Class and brake backlog, fitted on 2023 to 202520253,721+1.083.7245.7%11.58
Class and brake backlog, fitted on 2023 to 20252025 Q2-Q42,793+1.483.4748.4%9.24
Class and brake backlog, fitted on 2023 to 2025Loaded months1,322+2.185.5733.1%17.60
Class and brake backlog, fitted on 2023 to 2025Ordinary months9,674+1.093.1951.9%8.85
Class, brake backlog and brake standard hours, out of sample2023 to 202510,996+1.804.0147.9%9.33
Class, brake backlog and brake standard hours, out of sample20233,458+0.783.1353.5%8.41
Class, brake backlog and brake standard hours, out of sample20243,817+2.974.3249.4%8.41
Class, brake backlog and brake standard hours, out of sample20253,721+1.544.5141.1%11.12
Class, brake backlog and brake standard hours, out of sample2025 Q2-Q42,793+1.313.6047.2%9.42
Class, brake backlog and brake standard hours, out of sampleLoaded months1,322+5.388.9417.9%14.40
Class, brake backlog and brake standard hours, out of sampleOrdinary months9,674+1.313.3352.0%8.63
Class, brake backlog and lot size, out of sample2023 to 202510,996+1.824.0247.7%9.30
Class, brake backlog and lot size, out of sample20233,458+0.823.1453.2%8.37
Class, brake backlog and lot size, out of sample20243,817+3.014.3349.4%8.37
Class, brake backlog and lot size, out of sample20253,721+1.544.5141.0%11.12
Class, brake backlog and lot size, out of sample2025 Q2-Q42,793+1.323.6047.1%9.41
Class, brake backlog and lot size, out of sampleLoaded months1,322+5.368.9517.8%14.43
Class, brake backlog and lot size, out of sampleOrdinary months9,674+1.343.3451.8%8.60

Against the current quote, 2023 to 2025

QuoteShorter than the current quoteShorter by, days (mean)LongerLonger by, days (mean)Same
Class median96.6%4.100.0%3.4%
Class and brake backlog, out of sample88.4%4.177.0%4.404.6%
Class and brake backlog, fitted on 2023 to 202584.0%3.8614.1%3.631.9%
Class, brake backlog and brake standard hours, out of sample87.6%4.157.1%4.575.4%
Class, brake backlog and lot size, out of sample87.5%4.177.1%4.485.3%

How the out-of-sample quotes were reached

QuoteCell the quote was read fromQuotes at the floor
Class medianclass: 10,626 (96.6%); class standard (no history): 370 (3.4%)0 (0.0%)
Class and brake backlog, out of sampleown band: 9,500 (86.4%); nearest band: 1,099 (10.0%); class standard (no history): 370 (3.4%); class (no band with enough jobs): 27 (0.2%)0 (0.0%)
Class, brake backlog and brake standard hours, out of sampleown cell: 9,051 (82.3%); backlog band only: 1,575 (14.3%); class standard (no history): 370 (3.4%)0 (0.0%)
Class, brake backlog and lot size, out of sampleown cell: 9,052 (82.3%); backlog band only: 1,574 (14.3%); class standard (no history): 370 (3.4%)0 (0.0%)

Out of sample, each job is quoted the median lead time of non-rush jobs shipped before the first day of its release month, in its cell, rounded to whole days and never below the 10th percentile of lead time for the routing class. A cell with fewer than 30 earlier jobs takes the nearest brake backlog band that has them, the deeper band first. Job size is in thirds within the routing class.

Table 18. The recommended quote at the median and at the 80th percentile: jobs shipped within the quote and error

QuotePeriodJobs shipped within the quoteMean errorMean absolute errorWithin 2 daysMean quote
Current quote2023 to 202571.7%-1.514.7827.8%12.64
Current quoteLoaded months21.9%+5.847.3419.5%13.95
Current quoteOrdinary months78.5%-2.514.4429.0%12.46
Class and brake backlog, out of sample2023 to 202547.4%+1.864.0247.7%9.26
Class and brake backlog, out of sampleLoaded months33.1%+5.488.9417.8%14.31
Class and brake backlog, out of sampleOrdinary months49.4%+1.373.3551.8%8.57
Class and brake backlog at the 80th percentile, out of sample2023 to 202573.5%-1.754.7729.1%12.87
Class and brake backlog at the 80th percentile, out of sampleLoaded months46.4%+1.549.1512.9%18.24
Class and brake backlog at the 80th percentile, out of sampleOrdinary months77.2%-2.204.1831.3%12.14
Class and brake backlog, fitted on 2023 to 20252023 to 202552.5%+1.233.4849.6%9.90
Class and brake backlog, fitted on 2023 to 2025Loaded months44.9%+2.185.5733.1%17.60
Class and brake backlog, fitted on 2023 to 2025Ordinary months53.5%+1.093.1951.9%8.85
Class and brake backlog at the 80th percentile, fitted on 2023 to 20252023 to 202582.2%-3.354.9224.7%14.48
Class and brake backlog at the 80th percentile, fitted on 2023 to 2025Loaded months77.1%-3.566.3822.5%23.34
Class and brake backlog at the 80th percentile, fitted on 2023 to 2025Ordinary months82.9%-3.324.7225.0%13.27

Table 19. The quote grid with brake standard hours in thirds, fitted on 2023 to 2025: median lead time (jobs in the cell)

Routing classBrake standard hours on the jobUnder 1 days1 to 2 days2 to 3 days3 to 5 daysOver 5 days
Repeat partunder 1.177 (1,654)8 (677)11 (201)16 (94)18 (186)
Repeat part1.17 to 2.267 (1,716)8 (648)11 (215)15 (87)18 (146)
Repeat partover 2.267 (1,738)9 (613)11 (214)17 (87)18 (161)
New partunder 1.108 (202)9 (97)(29)(6)(18)
New part1.10 to 2.258 (231)9 (79)(19)(14)(9)
New partover 2.259 (217)11 (83)(18)(15)(20)
Outside processingunder 1.1313 (459)14 (187)19 (67)(20)26 (46)
Outside processing1.13 to 2.2113 (485)14 (173)22 (48)(27)28 (45)
Outside processingover 2.2114 (478)15 (186)18 (47)(28)25 (40)