1. Capacity and Constraints
The shop's floor consists of 25 machines across ten work centers. The press brakes are the busiest, with 16,165 machine hours in 2025 (36% of total). Machine hours break into operations per day and hours per operation, shown in routing order below.
Daily Floor Activity by Work Center, 2025
The press brakes consistently run at the highest utilization of any work center (average of 84% 2023-2025), followed by the robotic weld cell (70%). Across all work centers, average utilization increased from 63% in 2023 to 75% in 2025 as released work grew 18% (4,315 to 5,081 jobs a year; brake standard hours up 19%) across the same set of machines and shifts.
Average monthly utilization by work center, 2023 to 2025
Capacity Constraints
In 2025, the press brakes ran at 91% average utilization and the robotic weld cell at 82%. Against their 97% uptime, the average production capacity buffer was only 6 points for the press brakes and 15 points for the robotic weld cell, the smallest of all work centers. See Appendix Table 1 for additional detail.
Utilization and Machine Uptime by Work Center
With so little buffer, an ordinary heavy week can take the brakes and the weld cell to maximum utilization: they ran at or above 95% utilization in 31% and 37% of weeks in 2025, about twice as often as any other work center. This is explored in more detail in Section 2. See Appendix Table 2 for additional detail.
Share of weeks at or above 95% utilization, 2025
Throughout 2025, jobs spent 38,589 days waiting in queue at a work center. The press brake station accounted for 44% of those days, which is a function of its consistently high utilization, as well as its volume of operations. There were 5,566 press brake operations in 2025 (20% of total). The robotic weld cell, which also ran at high utilization, accounted for less than 5% of queue days, because only 420 operations (1.5% of total) passed through it.
Share of queue days by work center, 2025
The press brakes are therefore the shop's primary constraint on two counts: the highest utilization with the least buffer, and 44% of all queue days. The robotic weld cell spends more weeks at maximum utilization (19 against 16) and constrains the enclosure work that crosses it. These stations are examined in more detail throughout this report.
2. Load and Queue Time
Queue time at each work center is driven by one of two factors. At six work centers it is load: queue time is flat at low utilization, rises steadily as utilization increases, and rises sharply once utilization passes ~85%. At the other four work centers it is schedule: queue times are set by daily dispatch lists and do not move with load; these centers rarely operate near maximum utilization.
Queue Time per Operation by Work Center, 2025
Across the six work centers with load-driven queue times, we see that their queue times rise sharply when operating near maximum utilization. As shown in Section 1, the press brake operates at these levels 31% of weeks in a year, and robotic weld 37%.
Queue Time in Weeks at or Above 95% Utilization vs. Other Weeks
The queueing curve for each of these work centers shows a nonlinear (convex) relationship with a knee: flat and nearly linear at low utilization, then bending sharply upward and rising as utilization approaches 100%. The curve is fitted on rolling 13-week windows rather than single weeks because a week's queue carries the backlog of the weeks before it, so single weeks scatter around the curve (a week at 100% after a quiet month shows a short wait) while the windowed fit explains 45% of the variation at the brakes against 15% for single weeks.
The press brakes and the robotic weld cell are the two work centers above the knee most weeks: in 2025, they were above 85% utilization in 44 (85%) and 29 (56%) weeks. Both curves show an average queue time at 85% utilization (1.25 days for press brake, 2.35 days for robotic weld) that is significantly higher than the mean queue time at lower utilization bands (0.33 for press brake and 0.95 for robotic weld, below 80%). The brakes seldom run light, so their panel has few points below 70% (29 of 138 weeks); the weld cell, one machine on one shift, swings between idle and saturated weeks (20 below 80%, 19 at or above 95%), climbs faster with load (3.7 days on the curve at 90%) and ran above its curve in 2025 (2.87 days measured against 1.87). See Appendix Tables 3, 4 and 5 for additional detail.
Queue Time Against Utilization: Press brake and Robotic weld, 2023 to 2025
The brake center consists of five machines. Precision work and expedited jobs are routed to B1 and B2, so these two machines have the shortest queue times (2.6 and 2.5 days against 3.2 to 3.5 on B3 to B5) at about the same utilization (90% against 91% to 92%). The long brake waits that drive late jobs are concentrated on B3, B4, and B5, where jobs are routed without a priority queue. See Appendix Tables 6 and 7 for additional detail.
Queue Time per Operation by Individual Brakes, 2025
Assembly and the manual weld bays sit below the knee most weeks: in 2025 they were above 85% utilization in 18 (35%) and 9 (17%) weeks. Both show the same step as the brakes: at low utilization levels, mean queue time of 0.84 at assembly and 0.72 at manual weld against 2.24 and 1.68 at or above 85% utilization. The curve fits assembly less closely than the brakes (rank correlation 0.80 against 0.89) and the weld bays less closely again (0.62), since six bays pool arrivals until the last few points of load. See Appendix Tables 3, 5, 8 and 9 for additional detail.
Queue Time Against Utilization: Assembly and Manual weld, 2023 to 2025
The laser and the punch are first operations, so their queue is measured from traveler print to first cut, less any wait for material. The lasers pool three machines over about 83 operations a week and reach high utilization only when releases surge, with queue time increasing from 0.65 days below 80% utilization to 2.5 at or above 90%. The punch, one machine running about 16 operations a week, fills on a few large jobs, and queue time increases from 0.25 at low utilization to 1.91 at or above 85%. See Appendix Tables 3, 5, 10 and 11 for additional detail.
First-Operation Queue Time Against Utilization: Laser and Punch, 2023 to 2025
3. Brake Hours: Setups, Standards and the Peak
Sections 1 and 2 established the press brakes as the shop's primary constraint and mapped how their queue time rises with load. This section is aimed at the brake hours themselves: where hours are lost to setups running over standard and how many can be recovered, whether the standard hours the schedule is planned in are right, and where crewed hours fall short. The next report, Discrete Event Simulation: On-time Delivery, takes these measured hours as its inputs.
Utilization is running machine hours over hours available, and the shop controls both sides: how many hours each job takes, and how many hours are crewed. Downtime (9 hours a week at 97% uptime) and run time over standard (9 hours a week at 1.05 of standard) are small. Setups over standard are not: 36 hours a week, which is 10.4 points of brake utilization against the standards the schedule plans with, and about 7.8 points once the small-lot standards are corrected.
Brake Utilization and Queue Time on the Curve, With and Without Setup Overrun, 2025
Brake setups over standard
Setups over standard on the brakes ran 1,847 hours in 2025, with the median brake setup running at 1.16 of standard and the 90th percentile at 2.05. This overrun is unique to brakes: no other work center exceeds 51 setup hours over standard in the year or a median ratio of 1.00. See Appendix Table 12 for additional detail.
Four overlapping conditions drove most of the overrun. Setups handed over at a shift boundary are 13% of setups and 51% of the overrun. Lots under 25 pieces are 49% of setups and 67% of the overrun, because the setup standards under-plan small lots (median 1.28 against 1.05 on larger lots). First setups of a part by an operator run at 1.29 against 0.99 when the operator has set it up before. Enclosures and chassis run at 1.31 and 1.29 against 1.09 to 1.10 for panels and brackets. See Appendix Tables 13 to 17 for additional detail.
Share of Brake Setups Against Share of Overrun Hours by Condition, 2025
What can be recovered
Three changes recover 13.9 of the 36 hours a week, 4.1 points of brake utilization, taking the brakes from 91% to 87% and queue time on the curve from 2.34 to 1.46 days per operation. Running the top 12 part-operations by overrun at standard releases 8.1 hours a week; the rest of the overrun is spread across 1,943 part-operations. Assigning repeat setups to an operator who has set the part up before releases 4.3: first setups of a repeat part by a new operator ran at 1.58 of standard against 1.31 with prior familiarity. A handover standard, under which the operator who starts a setup finishes it or leaves a written handover at the machine, releases 1.5, the handover's own cost once long setups are set aside. The report Discrete Event Simulation: On-time Delivery carries these 13.9 hours as the setup program. See Appendix Tables 18 to 21 for additional detail.
Brake Hours a Week Released by Setup Lever, 2025
Planning standards
The schedule and the quote are built in standard hours, and the brake standards understate what the brakes actually run: the 2025 plan carried 13,940 brake hours against 15,967 run, a gap of 2,027 hours, or 11.4 points of utilization. Two corrections bring part of it onto the plan. Raising the setup standard on lots under 25 pieces by 23% adds 483 hours. Refreshing the 525 stale brake standards (those dated at the part's first quote, which run 10% further above standard than refreshed parts) adds 242. Together they close 36% of the gap, and the setup recovery above takes a further 724 hours off the actual. What remains, 578 hours, is the overrun the plan will still not see. See Appendix Tables 22 to 25 for additional detail.
Brake Hours: Planned Against Actual, 2025
Away from the constraint, the L2 and L3 lasers run at 0.82 of their run standard, so planned laser hours are overstated by 12.9%; setting those standards to measured is an estimating correction (Flow and On-time Delivery, Section 4) rather than a capacity one.
Where crewed hours fall short
Setup recovery adds 13.9 brake hours a week; the year-end peak needs far more. In the six weeks from November 11, 2024 the shop released 361 brake standard hours a week against 284 of crewed capacity, a shortfall of about 77 hours a week that went into the queue. Queue-triggered Saturday shifts covered almost none of it: 2 shifts in six weeks, 28 hours in total. A Saturday brake shift as the shop has worked it supplies 6.8 machine hours, 8% of the weekly gap; one with both B1 and B2 crewed supplies about 15, 17%. Discrete Event Simulation: On-time Delivery tests one every week from November through February. See Appendix Table 26 for additional detail.
Brake Hours Released Against Capacity by Week, Q4 2024 to Q1 2025
The robotic weld cell runs one shift at 82% utilization and is at or above 95% in 19 weeks of 52; its second shift is uncrewed. Enclosures are 78% of its hours, so a second shift would serve the enclosure customers first. The simulation report tests and prices crewing it. See Appendix Table 27 for additional detail.
Measured from the record: the brakes lose 36 hours a week to setups over standard, enough to put them above the knee of their curve on its own; 13.9 of those hours are recoverable by three changes; the small-lot setup standard, 546 stale standards and the L2 and L3 run standards misstate planned hours in known directions; the year-end peak releases about 77 brake hours a week more than the brakes can run; and the robotic weld cell's second shift is uncrewed. Discrete Event Simulation: On-time Delivery takes these as its inputs.
Appendix
Table 1. Utilization and machine uptime by work center
| Work center | Machines | Operations | Scheduled hours | Machine hours | Downtime hours | Available hours | Utilization | Uptime | Queue time, mean | Utilization, Q2-Q4 | Uptime, Q2-Q4 | Queue time, mean, Q2-Q4 |
|---|
| Press brake | 5 | 5,566 | 18,308 | 16,165 | 470 | 17,838 | 91% | 97% | 3.06 | 90% | 97% | 1.48 |
| Robotic weld | 1 | 420 | 1,992 | 1,583 | 57 | 1,935 | 82% | 97% | 2.87 | 83% | 97% | 3.21 |
| Laser | 3 | 4,334 | 10,152 | 7,359 | 329 | 9,823 | 75% | 97% | | 75% | 97% | |
| Assembly | 2 | 684 | 3,984 | 2,631 | 100 | 3,884 | 68% | 97% | 1.63 | 66% | 97% | 1.53 |
| Inspection and pack | 2 | 5,129 | 3,984 | 2,574 | 144 | 3,840 | 67% | 96% | 0.69 | 65% | 96% | 0.74 |
| Grind and deburr | 2 | 5,572 | 3,984 | 2,575 | 115 | 3,869 | 67% | 97% | 0.88 | 66% | 97% | 0.89 |
| Punch | 1 | 815 | 1,992 | 1,293 | 49 | 1,943 | 67% | 98% | | 64% | 98% | |
| Hardware | 2 | 2,118 | 3,984 | 2,547 | 83 | 3,901 | 65% | 98% | 0.83 | 65% | 98% | 0.84 |
| Manual weld | 6 | 1,533 | 11,952 | 7,567 | 346 | 11,606 | 65% | 97% | 0.87 | 62% | 97% | 0.76 |
| Powder coat | 1 | 2,328 | 2,052 | 1,111 | 53 | 1,999 | 56% | 97% | 0.50 | 54% | 98% | 0.43 |
Table 2. Weekly utilization at or above 95% by work center: weeks, queue time, jobs at the work center and share of hours
2025
| Work center | Utilization | Weeks at or above 95% | Of which full five-day weeks | Queue time in those weeks | Queue time in the other weeks | Jobs at the work center in those weeks, daily mean | Jobs at the work center in the other weeks, daily mean | Share of machine hours in those weeks |
|---|
| Press brake | 91% | 16 of 52 | 14 | 3.39 | 2.90 | 72.7 | 62.8 | 33% |
| Robotic weld | 82% | 19 of 52 | 14 | 4.11 | 2.25 | 7.7 | 4.3 | 42% |
| Laser | 75% | 4 of 52 | 2 | 5.38 | 1.12 | 113.4 | 47.1 | 8% |
| Assembly | 68% | 9 of 52 | 8 | 3.50 | 1.13 | 12.0 | 4.3 | 25% |
| Inspection and pack | 67% | 1 of 52 | 1 | 1.10 | 0.68 | 28.3 | 14.6 | 3% |
| Grind and deburr | 67% | 0 of 52 | 0 | | 0.88 | | 20.8 | 0% |
| Punch | 67% | 9 of 52 | 8 | 2.07 | 0.78 | 11.2 | 8.3 | 26% |
| Hardware | 65% | 0 of 52 | 0 | | 0.83 | | 9.0 | 0% |
| Manual weld | 65% | 1 of 52 | 1 | 0.66 | 0.87 | 12.3 | 9.0 | 3% |
| Powder coat | 56% | 0 of 52 | 0 | | 0.50 | | 14.6 | 0% |
2025 Q2-Q4
| Work center | Utilization | Weeks at or above 95% | Of which full five-day weeks | Queue time in those weeks | Queue time in the other weeks | Jobs at the work center in those weeks, daily mean | Jobs at the work center in the other weeks, daily mean | Share of machine hours in those weeks |
|---|
| Press brake | 90% | 12 of 39 | 10 | 1.91 | 1.27 | 40.2 | 31.4 | 33% |
| Robotic weld | 83% | 16 of 39 | 12 | 4.30 | 2.48 | 8.2 | 4.7 | 48% |
| Laser | 75% | 2 of 39 | 1 | 1.48 | 0.83 | 99.1 | 46.6 | 5% |
| Assembly | 66% | 4 of 39 | 4 | 3.83 | 1.12 | 14.7 | 4.3 | 16% |
| Grind and deburr | 66% | 0 of 39 | 0 | | 0.89 | | 21.2 | 0% |
| Inspection and pack | 65% | 1 of 39 | 1 | 1.10 | 0.73 | 28.3 | 15.3 | 4% |
| Hardware | 65% | 0 of 39 | 0 | | 0.84 | | 9.1 | 0% |
| Punch | 64% | 5 of 39 | 4 | 1.72 | 0.61 | 10.5 | 8.0 | 20% |
| Manual weld | 62% | 0 of 39 | 0 | | 0.76 | | 8.2 | 0% |
| Powder coat | 54% | 0 of 39 | 0 | | 0.43 | | 13.4 | 0% |
2023 to 2025
| Work center | Weeks at or above 95% | Queue time in those weeks | Queue time in the other weeks |
|---|
| Robotic weld | 39 of 155 | 3.58 | 1.66 |
| Press brake | 28 of 155 | 2.57 | 1.45 |
| Punch | 20 of 155 | 2.56 | 0.50 |
| Assembly | 18 of 155 | 3.60 | 1.06 |
| Laser | 11 of 155 | 3.95 | 0.93 |
| Manual weld | 7 of 155 | 2.37 | 0.96 |
| Grind and deburr | 1 of 155 | 0.71 | 0.83 |
| Hardware | 1 of 155 | 1.93 | 0.82 |
| Inspection and pack | 1 of 155 | 1.10 | 0.70 |
| Powder coat | 0 of 155 | | 0.48 |
Brake queue 90th percentile by quarter, 2025
Table 3. Weekly queue time by utilization band and work center, full weeks 2023 to 2025
| Work center | Utilization in the week | Weeks | Queue time, mean of weeks | Median |
|---|
| Press brake | below 80% | 46 | 0.33 | 0.28 |
| Press brake | 80% to 85% | 12 | 0.81 | 0.38 |
| Press brake | 85% to 90% | 15 | 1.77 | 1.02 |
| Press brake | 90% to 95% | 42 | 2.12 | 1.16 |
| Press brake | at or above 95% | 23 | 2.73 | 1.98 |
| Robotic weld | below 80% | 81 | 0.95 | 0.69 |
| Robotic weld | 80% to 85% | 10 | 3.28 | 2.77 |
| Robotic weld | 85% to 90% | 9 | 2.56 | 2.21 |
| Robotic weld | 90% to 95% | 6 | 2.97 | 2.49 |
| Robotic weld | at or above 95% | 30 | 3.43 | 2.73 |
| Laser | below 80% | 101 | 0.65 | 0.56 |
| Laser | 80% to 85% | 13 | 1.02 | 0.95 |
| Laser | 85% to 90% | 8 | 2.17 | 1.11 |
| Laser | 90% to 95% | 8 | 1.51 | 1.01 |
| Laser | at or above 95% | 8 | 3.48 | 2.60 |
| Assembly | below 80% | 97 | 0.84 | 0.74 |
| Assembly | 80% to 85% | 11 | 1.15 | 0.95 |
| Assembly | 85% to 90% | 7 | 1.27 | 1.02 |
| Assembly | 90% to 95% | 9 | 1.88 | 1.18 |
| Assembly | at or above 95% | 14 | 2.95 | 2.89 |
| Inspection and pack | below 80% | 131 | 0.68 | 0.68 |
| Inspection and pack | 80% to 85% | 2 | 0.80 | 0.80 |
| Inspection and pack | 85% to 90% | 4 | 0.68 | 0.68 |
| Inspection and pack | at or above 95% | 1 | 1.10 | 1.10 |
| Grind and deburr | below 80% | 129 | 0.78 | 0.75 |
| Grind and deburr | 80% to 85% | 5 | 0.79 | 0.78 |
| Grind and deburr | 85% to 90% | 3 | 1.36 | 1.07 |
| Grind and deburr | 90% to 95% | 1 | 0.85 | 0.85 |
| Punch | below 80% | 105 | 0.25 | 0.09 |
| Punch | 80% to 85% | 6 | 0.73 | 0.61 |
| Punch | 85% to 90% | 6 | 0.83 | 0.73 |
| Punch | 90% to 95% | 4 | 1.99 | 1.40 |
| Punch | at or above 95% | 17 | 2.27 | 1.55 |
| Hardware | below 80% | 125 | 0.77 | 0.76 |
| Hardware | 80% to 85% | 10 | 0.95 | 0.84 |
| Hardware | 85% to 90% | 2 | 0.81 | 0.81 |
| Hardware | 90% to 95% | 1 | 1.11 | 1.11 |
| Manual weld | below 80% | 109 | 0.72 | 0.66 |
| Manual weld | 80% to 85% | 6 | 1.59 | 1.22 |
| Manual weld | 85% to 90% | 6 | 0.90 | 0.92 |
| Manual weld | 90% to 95% | 12 | 1.82 | 1.08 |
| Manual weld | at or above 95% | 5 | 2.26 | 1.13 |
| Powder coat | below 80% | 137 | 0.47 | 0.40 |
| Powder coat | 85% to 90% | 1 | 0.97 | 0.97 |
Weeks of 2025 at or above 80% and 95% utilization
| Work center | Weeks at or above 80% | Weeks at or above 95% | Weeks in the year |
|---|
| Press brake | 46 | 16 | 52 |
| Robotic weld | 32 | 19 | 52 |
| Laser | 20 | 4 | 52 |
| Assembly | 21 | 9 | 52 |
| Inspection and pack | 7 | 1 | 52 |
| Grind and deburr | 5 | 0 | 52 |
| Punch | 18 | 9 | 52 |
| Hardware | 7 | 0 | 52 |
| Manual weld | 11 | 1 | 52 |
| Powder coat | 0 | 0 | 52 |
Table 4. Fitted queue time curve by work center
| Work center | Machines (m) | Scale k | R-squared, 13-week | Rank correlation | Utilization range fitted | R-squared, single weeks | Queue time at 75% | At 85% | At 90% | At 92% |
|---|
| Laser | 3 | 1.717 | 0.64 | 0.79 | 53% to 89% | 0.11 | 1.35 | 2.84 | 4.72 | 6.14 |
| Punch | 1 | 0.455 | 0.55 | 0.82 | 43% to 79% | 0.35 | 1.37 | 2.58 | 4.10 | 5.23 |
| Press brake | 5 | 1.399 | 0.45 | 0.89 | 69% to 95% | 0.15 | 0.55 | 1.25 | 2.16 | 2.85 |
| Robotic weld | 1 | 0.415 | 0.27 | 0.79 | 39% to 95% | -0.32 | 1.24 | 2.35 | 3.73 | 4.77 |
| Manual weld | 6 | 6.362 | 0.19 | 0.62 | 44% to 79% | -0.84 | 1.93 | 4.53 | 7.94 | 10.55 |
| Powder coat | 1 | 0.455 | -0.16 | 0.37 | 41% to 62% | -0.20 | 1.36 | 2.58 | 4.09 | 5.23 |
| Assembly | 2 | 1.337 | -0.33 | 0.80 | 41% to 89% | -0.12 | 1.76 | 3.52 | 5.74 | 7.41 |
| Hardware | 2 | 1.220 | -14.83 | 0.25 | 46% to 72% | -11.64 | 1.61 | 3.21 | 5.24 | 6.76 |
| Inspection and pack | 2 | 0.959 | -17.42 | -0.21 | 47% to 73% | -18.39 | 1.26 | 2.53 | 4.12 | 5.31 |
| Grind and deburr | 2 | 1.058 | -18.95 | 0.45 | 47% to 75% | -8.25 | 1.39 | 2.79 | 4.54 | 5.86 |
Table 5. Position of each work center on its curve
| Work center | Utilization | Queue time measured | Queue time on curve | Weeks at or above 95% | Utilization, Q2-Q4 | Queue time measured, Q2-Q4 | Queue time on curve, Q2-Q4 | Weeks at or above 95%, Q2-Q4 |
|---|
| Press brake | 91% | 3.06 | 2.34 | 16 of 52 | 90% | 1.48 | 2.21 | 12 of 39 |
| Robotic weld | 82% | 2.87 | 1.87 | 19 of 52 | 83% | 3.20 | 1.98 | 16 of 39 |
| Laser | 75% | 1.39 | 1.35 | 4 of 52 | 75% | 0.85 | 1.34 | 2 of 39 |
| Assembly | 68% | 1.63 | 1.18 | 9 of 52 | 66% | 1.53 | 1.09 | 4 of 39 |
| Inspection and pack | 67% | 0.69 | 0.82 | 1 of 52 | 65% | 0.74 | 0.75 | 1 of 39 |
| Grind and deburr | 67% | 0.88 | 0.88 | 0 of 52 | 66% | 0.89 | 0.85 | 0 of 39 |
| Punch | 67% | 1.06 | 0.91 | 9 of 52 | 64% | 0.79 | 0.82 | 5 of 39 |
| Hardware | 65% | 0.83 | 0.95 | 0 of 52 | 65% | 0.84 | 0.91 | 0 of 39 |
| Manual weld | 65% | 0.87 | 0.94 | 1 of 52 | 62% | 0.76 | 0.76 | 0 of 39 |
| Powder coat | 56% | 0.50 | 0.57 | 0 of 52 | 54% | 0.43 | 0.53 | 0 of 39 |
Table 6. Utilization and queue time for the five brakes and the robotic weld cell, 2025 and Q2-Q4
| Machine | Crewed shifts | Utilization, 2025 | Queue time, mean | Median | 90th percentile | Utilization, Q2-Q4 | Queue time, mean, Q2-Q4 | Median, Q2-Q4 | 90th percentile, Q2-Q4 |
|---|
| B1 | 2 | 89.7% | 2.59 | 0.87 | 8.3 | 89.8% | 1.26 | 0.47 | 3.4 |
| B2 | 2 | 90.4% | 2.47 | 0.60 | 8.2 | 92.1% | 1.17 | 0.44 | 3.4 |
| B3 | 2 | 90.7% | 3.38 | 1.18 | 10.1 | 89.6% | 1.74 | 0.72 | 4.9 |
| B4 | 2 | 91.7% | 3.19 | 1.07 | 9.7 | 90.1% | 1.50 | 0.52 | 4.2 |
| B5 | 1 | 90.7% | 3.48 | 1.15 | 10.8 | 88.2% | 1.62 | 0.92 | 4.1 |
| Robotic weld cell | 1 | 81.8% | 2.87 | 1.19 | 7.9 | 82.7% | 3.21 | 1.27 | 9.1 |
Table 7. The brakes and the robotic weld cell: hours and utilization on both bases
| Machine | Weekday scheduled hours | Saturday and extended hours | Machine hours | Downtime hours | Utilization | Utilization, weekday basis | Uptime | Operations | Utilization, Q2-Q4 | Weekday basis, Q2-Q4 |
|---|
| B1 | 3,984 | 190 | 3,647 | 110 | 89.7% | 94.1% | 97% | 975 | 89.8% | 91.8% |
| B2 | 3,984 | 190 | 3,672 | 111 | 90.4% | 94.8% | 97% | 941 | 92.1% | 94.2% |
| B3 | 3,984 | 0 | 3,523 | 100 | 90.7% | 90.7% | 97% | 1,466 | 89.6% | 89.6% |
| B4 | 3,984 | 0 | 3,556 | 107 | 91.7% | 91.7% | 97% | 1,358 | 90.1% | 90.1% |
| B5 | 1,992 | 0 | 1,768 | 43 | 90.7% | 90.7% | 98% | 826 | 88.2% | 88.2% |
| Robotic weld cell | 1,992 | 0 | 1,583 | 57 | 81.8% | 81.8% | 97% | 420 | 82.7% | 82.7% |
Table 8. Queue days by work center and driver of queue time, 2025
| Work center | Driver of queue time | Operations | Queue days | Share |
|---|
| Press brake | Load-driven | 5,566 | 17,013 | 44% |
| Laser (first operation) | Load-driven | 4,334 | 5,771 | 15% |
| Grind and deburr | Schedule-driven | 5,572 | 4,902 | 13% |
| Inspection and pack | Schedule-driven | 5,129 | 3,526 | 9% |
| Hardware | Schedule-driven | 2,118 | 1,748 | 5% |
| Manual weld | Load-driven | 1,533 | 1,328 | 3% |
| Robotic weld | Load-driven | 420 | 1,207 | 3% |
| Powder coat | Schedule-driven | 2,328 | 1,163 | 3% |
| Assembly | Load-driven | 684 | 1,115 | 3% |
| Punch (first operation) | Load-driven | 815 | 816 | 2% |
| All | | | 38,589 | 100% |
Table 9. Assembly: hot weeks, where its work comes from, and the weekly correlations
By year
| Year | Utilization | Queue time | Weeks at or above 95% | Operations |
|---|
| 2023* | 54% | 1.47 | 3 of 51 | 541 |
| 2024 | 62% | 1.18 | 6 of 52 | 579 |
| 2025 | 68% | 1.63 | 9 of 52 | 684 |
* 2023 includes the first four weeks of the record, when jobs already in process raise the queue time; from the week of January 30 the 2023 queue time is 1.00 days per operation.
Weeks at or above 95% against the other weeks, 2025
| Weeks at or above 95% | Other weeks |
|---|
| Weeks | 9 | 43 |
| Utilization | 99% | 61% |
| Queue time | 3.50 | 1.13 |
| Arrivals a week | 14.2 | 12.7 |
| Arrivals a week on jobs routed through the robotic weld cell | 2.3 | 2.3 |
| Robotic weld cell share of arrivals | 16% | 18% |
| Machine hours per operation | 4.48 | 3.65 |
Where assembly's work comes from, 2025
| Weld on the job's routing | Operations | Share of assembly hours | Queue time | 90th percentile |
|---|
| No weld | 366 | 57% | 1.86 | 5.0 |
| Manual weld bays | 200 | 29% | 1.40 | 3.1 |
| Robotic weld cell | 118 | 13% | 1.31 | 3.0 |
| Operation before assembly | Share of assembly operations |
|---|
| Powder coat | 48% |
| Outside processing | 25% |
| Grind and deburr | 14% |
| Press brake | 8% |
| Hardware | 5% |
Hours by part family, 2025
| Part family | Operations | Machine hours | Share of hours |
|---|
| Assembly | 523 | 2,079 | 79% |
| Enclosure | 161 | 539 | 21% |
Weekly correlations
| Across the weeks of 2025 | Correlation |
|---|
| Assembly utilization and assembly queue | 0.62 |
| Assembly utilization and arrivals in the week | 0.53 |
| Assembly utilization and arrivals from robotic weld routings | 0.18 |
| Assembly utilization and robotic weld cell hours, same week | 0.13 |
| The same, robotic weld cell hours one week earlier | 0.01 |
| The same, two weeks earlier | -0.01 |
Table 10. Laser weeks, November and December 2024
| Week starting | Working weekdays | Laser utilization | First operations started | First-operation queue time, mean | 90th percentile |
|---|
| 2024-11-04 | 5 | 75% | 82 | 0.72 | 2.2 |
| 2024-11-11 | 5 | 97% | 61 | 2.12 | 5.1 |
| 2024-11-18 | 5 | 95% | 117 | 3.07 | 7.4 |
| 2024-11-25 | 3 | 84% | 23 | 1.05 | 3.7 |
| 2024-12-02 | 5 | 79% | 97 | 3.82 | 8.5 |
| 2024-12-09 | 5 | 95% | 111 | 4.17 | 11.3 |
| 2024-12-16 | 5 | 96% | 106 | 6.17 | 13.7 |
Table 11. The lasers: first-operation queue time and material wait by month, and the three machines
By month, 2025
| Month of the first cut | First operations | First-operation queue time, mean | 90th percentile | Material wait, mean | First operations with a material wait | Laser utilization |
|---|
| January | 476 | 5.62 | 15.3 | 1.03 | 37% | 81% |
| February | 355 | 0.87 | 2.2 | 0.98 | 38% | 76% |
| March | 324 | 0.71 | 2.0 | 0.79 | 33% | 68% |
| April | 335 | 0.68 | 2.1 | 0.70 | 33% | 69% |
| May | 379 | 0.69 | 2.2 | 0.72 | 34% | 78% |
| June | 353 | 0.54 | 1.5 | 0.83 | 32% | 65% |
| July | 315 | 0.83 | 2.3 | 0.83 | 37% | 69% |
| August | 317 | 1.18 | 3.6 | 0.91 | 34% | 81% |
| September | 388 | 1.31 | 4.9 | 0.78 | 28% | 78% |
| October | 409 | 0.61 | 1.8 | 0.80 | 35% | 73% |
| November | 344 | 0.83 | 2.3 | 0.76 | 35% | 80% |
| December | 145 | 1.36 | 5.2 | 1.37 | 41% | 83% |
| 2025 | 4,140 | 1.39 | 4.3 | 0.85 | 35% | |
| 2025 Q2-Q4 | 2,985 | 0.86 | 2.5 | 0.82 | 34% | |
The three machines, 2025
| Laser | Scheduled hours | Machine hours | Share of laser hours | Utilization | Uptime | Run hours | Run standard hours | Run hours over standard | Share of laser standard hours |
|---|
| L1 | 1,992 | 1,689 | 23% | 90% | 94% | 1,557 | 1,519 | 1.03 | 20% |
| L2 | 3,984 | 2,867 | 39% | 74% | 97% | 2,493 | 3,021 | 0.83 | 40% |
| L3 | 3,984 | 2,804 | 38% | 72% | 98% | 2,439 | 2,989 | 0.82 | 40% |
| All | 9,960 | 7,359 | 100% | | | 6,488 | 7,529 | 0.86 | 100% |
Table 12. Setup against standard by work center
| Work center | Setups | Median ratio | Hours over standard ratio | 90th percentile | Setup hours | Standard hours | Overrun hours |
|---|
| Press brake | 5,249 | 1.16 | 1.44 | 2.05 | 5,998 | 4,151 | 1,847 |
| Grind and deburr | 5,202 | 1.00 | 1.05 | 1.42 | 1,091 | 1,040 | 51 |
| Manual weld | 1,421 | 1.00 | 1.05 | 1.40 | 748 | 710 | 37 |
| Laser | 4,057 | 1.00 | 1.04 | 1.33 | 844 | 811 | 33 |
| Inspection and pack | 4,767 | 1.00 | 1.04 | 1.44 | 747 | 715 | 32 |
| Powder coat | 2,176 | 1.00 | 1.06 | 1.40 | 574 | 544 | 30 |
| Hardware | 1,966 | 1.00 | 1.05 | 1.40 | 518 | 492 | 27 |
| Punch | 761 | 1.00 | 1.04 | 1.40 | 397 | 380 | 16 |
| Robotic weld | 392 | 1.00 | 1.03 | 1.42 | 486 | 470 | 15 |
| Assembly | 648 | 1.00 | 1.04 | 1.39 | 203 | 194 | 8 |
Table 13. Brake setup against standard by period
| Period | Setups | Median ratio | Hours over standard ratio | 90th percentile | Setup hours | Standard hours | Overrun hours |
|---|
| 2025 | 5,249 | 1.16 | 1.44 | 2.05 | 5,998 | 4,151 | 1,847 |
| 2025 Q2-Q4 | 3,823 | 1.18 | 1.45 | 2.05 | 4,396 | 3,027 | 1,369 |
| 2025 Q1 | 1,426 | 1.12 | 1.42 | 2.05 | 1,602 | 1,124 | 478 |
Table 14. Brake setups handed over at a shift boundary, and by time left in the shift at the start
| Setup | Setups | Median ratio | Hours over standard ratio | 90th percentile | Setup hours | Standard hours | Overrun hours | Share of setups | Share of overrun |
|---|
| Not handed over | 4,569 | 1.11 | 1.26 | 1.83 | 4,478 | 3,568 | 910 | 87.0% | 49.3% |
| Handed over at a shift boundary | 680 | 1.77 | 2.61 | 6.49 | 1,519 | 583 | 937 | 13.0% | 50.7% |
| Afternoon (14:00 to 14:30) | 304 | 1.69 | 2.53 | 6.40 | 662 | 262 | 400 | 5.8% | 21.7% |
| Overnight (22:30 to 06:00) | 306 | 1.71 | 2.66 | 7.30 | 706 | 266 | 440 | 5.8% | 23.8% |
| Other | 70 | 2.25 | 2.75 | 4.06 | 151 | 55 | 96 | 1.3% | 5.2% |
| Two-person setup, not handed over | 52 | 1.20 | 1.28 | 1.91 | 55 | 43 | 12 | 1.0% | 0.6% |
| Time left in the shift at setup start | Setups | Handed over | Median ratio | Hours over standard ratio |
|---|
| Last 30 minutes | 310 | 81.0% | 1.31 | 1.54 |
| 30 to 60 minutes | 325 | 54.2% | 1.34 | 1.58 |
| 1 to 2 hours | 643 | 17.1% | 1.13 | 1.46 |
| 2 to 4 hours | 1,340 | 5.0% | 1.14 | 1.46 |
| Over 4 hours | 2,620 | 2.6% | 1.15 | 1.40 |
Table 15. Brake setups by lot-size band
| Lot size | Setups | Median ratio | Hours over standard ratio | 90th percentile | Setup hours | Standard hours | Overrun hours | Median ratio, Q2-Q4 |
|---|
| Under 25 | 2,573 | 1.28 | 1.61 | 2.26 | 3,257 | 2,029 | 1,228 | 1.30 |
| 25 to 99 | 2,014 | 1.05 | 1.29 | 1.80 | 2,059 | 1,600 | 459 | 1.06 |
| 100 and over | 662 | 1.05 | 1.31 | 1.78 | 682 | 522 | 160 | 1.07 |
Table 16. Brake setups by the operator's prior setups of the part
| Prior setups | Setups | Median ratio | Hours over standard ratio | 90th percentile | Setup hours | Standard hours | Overrun hours | Median ratio, Q2-Q4 |
|---|
| None | 2,361 | 1.29 | 1.58 | 2.24 | 2,924 | 1,855 | 1,069 | 1.32 |
| 1 or 2 | 1,017 | 0.99 | 1.30 | 1.81 | 1,048 | 809 | 239 | 1.00 |
| 3 or more | 1,871 | 1.10 | 1.36 | 1.90 | 2,025 | 1,487 | 539 | 1.12 |
Table 17. Brake setups by part family
| Family | Setups | Median ratio | Hours over standard ratio | 90th percentile | Setup hours | Standard hours | Overrun hours | Median ratio, Q2-Q4 |
|---|
| Assembly | 475 | 1.11 | 1.36 | 2.12 | 579 | 427 | 153 | 1.16 |
| Bracket | 1,102 | 1.09 | 1.35 | 1.80 | 921 | 680 | 241 | 1.12 |
| Chassis | 485 | 1.29 | 1.62 | 2.36 | 731 | 452 | 279 | 1.31 |
| Enclosure | 1,035 | 1.31 | 1.58 | 2.23 | 1,492 | 942 | 550 | 1.30 |
| Panel | 1,190 | 1.10 | 1.35 | 1.92 | 1,180 | 876 | 304 | 1.12 |
| Weldment | 962 | 1.14 | 1.41 | 2.09 | 1,094 | 773 | 321 | 1.19 |
Table 18. The top 12 setup reduction candidates by overrun hours times work center utilization, 2025
| Part | Operation | Family | Setups | Mean lot | Setup hours | Standard hours | Median ratio | Overrun hours | Brake hours a week at standard |
|---|
| P-104146 | 20 | Panel | 192 | 51 | 251.3 | 167.0 | 1.26 | 84.3 | 1.62 |
| P-104050 | 40 | Enclosure | 162 | 47 | 197.6 | 118.3 | 1.30 | 79.4 | 1.53 |
| P-104050 | 20 | Enclosure | 159 | 47 | 187.8 | 127.2 | 1.27 | 60.6 | 1.16 |
| P-104062 | 20 | Chassis | 30 | 78 | 73.2 | 34.5 | 1.65 | 38.7 | 0.74 |
| P-104084 | 30 | Weldment | 95 | 52 | 124.2 | 89.3 | 0.99 | 34.9 | 0.67 |
| P-104162 | 30 | Weldment | 79 | 35 | 89.0 | 68.7 | 1.02 | 20.2 | 0.39 |
| P-104111 | 30 | Weldment | 55 | 53 | 66.7 | 47.9 | 1.25 | 18.8 | 0.36 |
| P-104422 | 30 | Enclosure | 21 | 44 | 45.6 | 27.1 | 1.30 | 18.5 | 0.36 |
| P-104130 | 30 | Weldment | 42 | 42 | 43.1 | 24.8 | 1.24 | 18.4 | 0.35 |
| P-106365 | 30 | Bracket | 4 | 15 | 19.4 | 2.6 | 7.42 | 16.7 | 0.32 |
| P-104294 | 30 | Chassis | 21 | 38 | 36.0 | 19.7 | 1.45 | 16.3 | 0.31 |
| P-104006 | 30 | Weldment | 26 | 28 | 35.8 | 20.8 | 1.31 | 15.0 | 0.29 |
Table 19. Setup reduction candidates, top 20
| Work center | Part | Operation | Family | Setups | Mean lot | Setup hours | Standard hours | Median ratio | Overrun hours | Utilization | Score | Hours a week at standard |
|---|
| Press brake | P-104146 | 20 | Panel | 192 | 51 | 251.3 | 167.0 | 1.26 | 84.3 | 91% | 76.4 | 1.62 |
| Press brake | P-104050 | 40 | Enclosure | 162 | 47 | 197.6 | 118.3 | 1.30 | 79.4 | 91% | 71.9 | 1.53 |
| Press brake | P-104050 | 20 | Enclosure | 159 | 47 | 187.8 | 127.2 | 1.27 | 60.6 | 91% | 54.9 | 1.16 |
| Press brake | P-104062 | 20 | Chassis | 30 | 78 | 73.2 | 34.5 | 1.65 | 38.7 | 91% | 35.1 | 0.74 |
| Press brake | P-104084 | 30 | Weldment | 95 | 52 | 124.2 | 89.3 | 0.99 | 34.9 | 91% | 31.6 | 0.67 |
| Press brake | P-104162 | 30 | Weldment | 79 | 35 | 89.0 | 68.7 | 1.02 | 20.2 | 91% | 18.3 | 0.39 |
| Press brake | P-104111 | 30 | Weldment | 55 | 53 | 66.7 | 47.9 | 1.25 | 18.8 | 91% | 17.0 | 0.36 |
| Press brake | P-104422 | 30 | Enclosure | 21 | 44 | 45.6 | 27.1 | 1.30 | 18.5 | 91% | 16.7 | 0.36 |
| Press brake | P-104130 | 30 | Weldment | 42 | 42 | 43.1 | 24.8 | 1.24 | 18.4 | 91% | 16.6 | 0.35 |
| Press brake | P-106365 | 30 | Bracket | 4 | 15 | 19.4 | 2.6 | 7.42 | 16.7 | 91% | 15.2 | 0.32 |
| Press brake | P-104294 | 30 | Chassis | 21 | 38 | 36.0 | 19.7 | 1.45 | 16.3 | 91% | 14.8 | 0.31 |
| Press brake | P-104006 | 30 | Weldment | 26 | 28 | 35.8 | 20.8 | 1.31 | 15.0 | 91% | 13.6 | 0.29 |
| Press brake | P-104203 | 30 | Enclosure | 18 | 48 | 32.4 | 18.2 | 1.58 | 14.2 | 91% | 12.9 | 0.27 |
| Press brake | P-104401 | 30 | Chassis | 4 | 65 | 17.5 | 3.8 | 4.73 | 13.7 | 91% | 12.5 | 0.26 |
| Press brake | P-104203 | 60 | Enclosure | 20 | 41 | 30.6 | 17.4 | 1.70 | 13.2 | 91% | 11.9 | 0.25 |
| Press brake | P-104762 | 20 | Weldment | 11 | 32 | 20.1 | 7.3 | 1.11 | 12.8 | 91% | 11.6 | 0.25 |
| Press brake | P-108101 | 30 | Enclosure | 8 | 98 | 19.2 | 7.5 | 1.42 | 11.7 | 91% | 10.6 | 0.22 |
| Press brake | P-104309 | 30 | Assembly | 37 | 30 | 51.1 | 40.0 | 1.19 | 11.1 | 91% | 10.1 | 0.21 |
| Press brake | P-120568 | 20 | Chassis | 1 | 20 | 11.6 | 0.9 | 12.36 | 10.7 | 91% | 9.7 | 0.21 |
| Press brake | P-104294 | 40 | Chassis | 19 | 40 | 25.6 | 15.2 | 1.44 | 10.4 | 91% | 9.4 | 0.20 |
Table 20. First setups of repeat parts where another operator had set the part up
| Setups | Count | Setup hours | Standard hours | Hours over standard ratio | Ratio of setups with prior familiarity, same lot band and family | Brake hours a week released | Share of brake machine hours |
|---|
| First setups of a part by the operator, all brake setups | 2,361 | 2,924 | 1,855 | 1.58 | | | |
| Of which repeat parts | 1,372 | 1,689 | 1,068 | 1.58 | 1.31 | 5.5 | 1.8% |
| Another current brake operator had set the part up, any shift | 1,079 | 1,319 | 834 | 1.58 | 1.31 | 4.3 | 1.4% |
| Another current brake operator on the same shift had set the part up | 769 | 926 | 595 | 1.56 | 1.31 | 2.8 | 0.9% |
Table 21. Brake hours released: the handover and the candidate list
| Estimate | Basis | Brake hours a year | Brake hours a week | Share of brake machine hours |
|---|
| Handed-over setups at the median ratio of setups not handed over | ratio 1.11 on 680 setups | 875 | 16.8 | 5.4% |
| Setups started in the last hour of a shift at the ratio of setups started earlier | hours-weighted ratio 1.58 against 1.43 on 644 setups, 68% handed over | 79 | 1.5 | 0.5% |
| Top 12 setup reduction candidates at standard | 886 setups | 422 | 8.1 | 2.6% |
Table 22. Run actual against standard by work center and laser
| Work center | Operations | Run hours | Standard run hours | Actual over standard | Actual over standard, Q2-Q4 |
|---|
| Laser | 4,334 | 6,488 | 7,529 | 0.862 | 0.863 |
| Manual weld | 1,533 | 6,687 | 6,652 | 1.005 | 0.998 |
| Assembly | 684 | 2,415 | 2,384 | 1.013 | 1.010 |
| Hardware | 2,118 | 2,029 | 1,999 | 1.015 | 1.021 |
| Punch | 815 | 898 | 879 | 1.022 | 1.016 |
| Inspection and pack | 5,129 | 1,833 | 1,756 | 1.044 | 1.045 |
| Grind and deburr | 5,572 | 1,491 | 1,425 | 1.047 | 1.053 |
| Press brake | 5,566 | 10,203 | 9,743 | 1.047 | 1.051 |
| Robotic weld | 420 | 1,101 | 1,040 | 1.059 | 1.052 |
| Powder coat | 2,328 | 541 | 505 | 1.071 | 1.070 |
| Machine | Operations | Run hours | Standard run hours | Actual over standard |
|---|
| Laser L1 | 872 | 1,557 | 1,519 | 1.025 |
| Laser L2 | 1,752 | 2,493 | 3,021 | 0.825 |
| Laser L3 | 1,710 | 2,439 | 2,989 | 0.816 |
Table 23. Stale-standard parts against refreshed parts
| Work center | Operations on stale-standard parts | Run ratio, stale | Run ratio, refreshed | Gap | Setup ratio, stale | Setup ratio, refreshed |
|---|
| Assembly | 208 | 1.130 | 0.964 | +17.2% | 1.037 | 0.970 |
| Grind and deburr | 1,307 | 1.155 | 1.012 | +14.1% | 0.982 | 0.980 |
| Hardware | 460 | 1.081 | 0.998 | +8.4% | 0.996 | 0.976 |
| Inspection and pack | 1,184 | 1.095 | 1.026 | +6.7% | 0.978 | 0.969 |
| Laser | 1,025 | 0.908 | 0.847 | +7.2% | 0.958 | 0.980 |
| Powder coat | 503 | 1.170 | 1.053 | +11.2% | 0.990 | 0.985 |
| Press brake | 1,233 | 1.127 | 1.023 | +10.1% | 1.383 | 1.359 |
| Punch | 186 | 1.068 | 1.013 | +5.4% | 0.934 | 0.984 |
| Robotic weld | 166 | 1.181 | 1.000 | +18.0% | 0.947 | 0.974 |
| Manual weld | 306 | 1.086 | 0.982 | +10.5% | 1.002 | 0.971 |
Table 24. Planned operation hours with standards refreshed
| Work center | Planned hours | With stale standards refreshed | Change |
|---|
| Assembly | 2,498 | 2,605 | +4.3% |
| Grind and deburr | 2,505 | 2,554 | +1.9% |
| Hardware | 2,487 | 2,524 | +1.5% |
| Inspection and pack | 2,465 | 2,493 | +1.1% |
| Laser | 8,330 | 8,453 | +1.5% |
| Powder coat | 1,069 | 1,078 | +0.8% |
| Press brake | 13,940 | 14,181 | +1.7% |
| Punch | 1,280 | 1,283 | +0.2% |
| Robotic weld | 1,521 | 1,574 | +3.5% |
| Manual weld | 7,319 | 7,477 | +2.2% |
| Laser | Hours | Change |
|---|
| Planned laser hours, current standards | 8,330 | +0.0% |
| With L2 and L3 run standards set to measured | 7,258 | -12.9% |
| With stale parts refreshed | 8,453 | +1.5% |
| With both | 7,381 | -11.4% |
Table 25. Standard hours per job with standards refreshed, by routing class
| Routing class | Jobs | Jobs for stale-standard parts | Standard hours per job | Stale parts refreshed, all jobs | Stale parts refreshed, their jobs | L2 and L3 set to measured | Both |
|---|
| All | 5,242 | 1,251 | 8.28 | +1.9% | +8.0% | -2.5% | -0.6% |
| Repeat part | 3,778 | 809 | 8.23 | +1.7% | +8.0% | -2.4% | -0.7% |
| New part | 444 | 131 | 9.03 | +2.0% | +7.7% | -2.5% | -0.5% |
| Outside processing | 1,020 | 311 | 8.15 | +2.5% | +8.0% | -2.8% | -0.2% |
Table 26. Brake standard hours released against crewed brake capacity, the six weeks from November 11, 2024
| Week starting | Working weekdays | Brake standard hours released | Crewed capacity net of downtime, standard hours | Shortfall | Saturday brake shifts | Extended hours | Saturday and extended machine hours |
|---|
| 2024-11-11 | 5 | 459 | 304 | 155 | 1 | 0 | 16 |
| 2024-11-18 | 5 | 334 | 305 | 29 | 0 | 0 | 0 |
| 2024-11-25 | 3 | 247 | 185 | 61 | 0 | 0 | 0 |
| 2024-12-02 | 5 | 253 | 298 | -45 | 0 | 0 | 0 |
| 2024-12-09 | 5 | 420 | 306 | 114 | 1 | 0 | 16 |
| 2024-12-16 | 5 | 455 | 306 | 149 | 0 | 0 | 0 |
| A week, on average | | 361 | 284 | 77 | 2 in all | 0 in all | 32 in all |
Table 27. The robotic weld cell: weeks by utilization band, hours by part family, setup and run against standard
Weeks by utilization band, 2025
| Utilization in the week | Weeks | Of which full five-day weeks | Operations | Queue time |
|---|
| below 80% | 20 | 19 | 144 | 1.20 |
| 80% to 85% | 3 | 3 | 26 | 3.33 |
| 85% to 90% | 5 | 5 | 58 | 3.20 |
| 90% to 95% | 5 | 5 | 51 | 3.56 |
| at or above 95% | 19 | 14 | 141 | 4.11 |
Hours by part family, 2025
| Part family | Operations | Machine hours | Share of hours | Queue time |
|---|
| Enclosure | 306 | 1,240 | 78% | 2.80 |
| Weldment | 57 | 138 | 9% | 2.63 |
| Chassis | 27 | 103 | 6% | 3.61 |
| Assembly | 18 | 62 | 4% | 2.72 |
| Panel | 4 | 25 | 2% | 4.74 |
| Bracket | 8 | 19 | 1% | 4.21 |
Setup and run against standard, 2025
| Hours | Standard hours | Hours over standard |
|---|
| Setup | 486 | 470 | 1.03 |
| Run | 1,101 | 1,040 | 1.06 |