1. Capacity and Constraints

The shop's floor consists of 25 machines across ten work centers. The press brakes are the busiest, with 16,165 machine hours in 2025 (36% of total). Machine hours break into operations per day and hours per operation, shown in routing order below.

Daily Floor Activity by Work Center, 2025
Daily Floor Activity by Work Center, 2025

The press brakes consistently run at the highest utilization of any work center (average of 84% 2023-2025), followed by the robotic weld cell (70%). Across all work centers, average utilization increased from 63% in 2023 to 75% in 2025 as released work grew 18% (4,315 to 5,081 jobs a year; brake standard hours up 19%) across the same set of machines and shifts.

Average monthly utilization by work center, 2023 to 2025
Average monthly utilization by work center, 2023 to 2025

Capacity Constraints

In 2025, the press brakes ran at 91% average utilization and the robotic weld cell at 82%. Against their 97% uptime, the average production capacity buffer was only 6 points for the press brakes and 15 points for the robotic weld cell, the smallest of all work centers. See Appendix Table 1 for additional detail.

Utilization and Machine Uptime by Work Center
Utilization and Machine Uptime by Work Center

With so little buffer, an ordinary heavy week can take the brakes and the weld cell to maximum utilization: they ran at or above 95% utilization in 31% and 37% of weeks in 2025, about twice as often as any other work center. This is explored in more detail in Section 2. See Appendix Table 2 for additional detail.

Share of weeks at or above 95% utilization, 2025
Share of weeks at or above 95% utilization, 2025

Throughout 2025, jobs spent 38,589 days waiting in queue at a work center. The press brake station accounted for 44% of those days, which is a function of its consistently high utilization, as well as its volume of operations. There were 5,566 press brake operations in 2025 (20% of total). The robotic weld cell, which also ran at high utilization, accounted for less than 5% of queue days, because only 420 operations (1.5% of total) passed through it.

Share of queue days by work center, 2025
Share of queue days by work center, 2025

The press brakes are therefore the shop's primary constraint on two counts: the highest utilization with the least buffer, and 44% of all queue days. The robotic weld cell spends more weeks at maximum utilization (19 against 16) and constrains the enclosure work that crosses it. These stations are examined in more detail throughout this report.

2. Load and Queue Time

Queue time at each work center is driven by one of two factors. At six work centers it is load: queue time is flat at low utilization, rises steadily as utilization increases, and rises sharply once utilization passes ~85%. At the other four work centers it is schedule: queue times are set by daily dispatch lists and do not move with load; these centers rarely operate near maximum utilization.

Queue Time per Operation by Work Center, 2025
Queue Time per Operation by Work Center, 2025

Across the six work centers with load-driven queue times, we see that their queue times rise sharply when operating near maximum utilization. As shown in Section 1, the press brake operates at these levels 31% of weeks in a year, and robotic weld 37%.

Queue Time in Weeks at or Above 95% Utilization vs. Other Weeks
Queue Time in Weeks at or Above 95% Utilization vs. Other Weeks

The queueing curve for each of these work centers shows a nonlinear (convex) relationship with a knee: flat and nearly linear at low utilization, then bending sharply upward and rising as utilization approaches 100%. The curve is fitted on rolling 13-week windows rather than single weeks because a week's queue carries the backlog of the weeks before it, so single weeks scatter around the curve (a week at 100% after a quiet month shows a short wait) while the windowed fit explains 45% of the variation at the brakes against 15% for single weeks.

The press brakes and the robotic weld cell are the two work centers above the knee most weeks: in 2025, they were above 85% utilization in 44 (85%) and 29 (56%) weeks. Both curves show an average queue time at 85% utilization (1.25 days for press brake, 2.35 days for robotic weld) that is significantly higher than the mean queue time at lower utilization bands (0.33 for press brake and 0.95 for robotic weld, below 80%). The brakes seldom run light, so their panel has few points below 70% (29 of 138 weeks); the weld cell, one machine on one shift, swings between idle and saturated weeks (20 below 80%, 19 at or above 95%), climbs faster with load (3.7 days on the curve at 90%) and ran above its curve in 2025 (2.87 days measured against 1.87). See Appendix Tables 3, 4 and 5 for additional detail.

Queue Time Against Utilization: Press brake and Robotic weld, 2023 to 2025
Queue Time Against Utilization: Press brake and Robotic weld, 2023 to 2025

The brake center consists of five machines. Precision work and expedited jobs are routed to B1 and B2, so these two machines have the shortest queue times (2.6 and 2.5 days against 3.2 to 3.5 on B3 to B5) at about the same utilization (90% against 91% to 92%). The long brake waits that drive late jobs are concentrated on B3, B4, and B5, where jobs are routed without a priority queue. See Appendix Tables 6 and 7 for additional detail.

Queue Time per Operation by Individual Brakes, 2025
Queue Time per Operation by Individual Brakes, 2025

Assembly and the manual weld bays sit below the knee most weeks: in 2025 they were above 85% utilization in 18 (35%) and 9 (17%) weeks. Both show the same step as the brakes: at low utilization levels, mean queue time of 0.84 at assembly and 0.72 at manual weld against 2.24 and 1.68 at or above 85% utilization. The curve fits assembly less closely than the brakes (rank correlation 0.80 against 0.89) and the weld bays less closely again (0.62), since six bays pool arrivals until the last few points of load. See Appendix Tables 3, 5, 8 and 9 for additional detail.

Queue Time Against Utilization: Assembly and Manual weld, 2023 to 2025
Queue Time Against Utilization: Assembly and Manual weld, 2023 to 2025

The laser and the punch are first operations, so their queue is measured from traveler print to first cut, less any wait for material. The lasers pool three machines over about 83 operations a week and reach high utilization only when releases surge, with queue time increasing from 0.65 days below 80% utilization to 2.5 at or above 90%. The punch, one machine running about 16 operations a week, fills on a few large jobs, and queue time increases from 0.25 at low utilization to 1.91 at or above 85%. See Appendix Tables 3, 5, 10 and 11 for additional detail.

First-Operation Queue Time Against Utilization: Laser and Punch, 2023 to 2025
First-Operation Queue Time Against Utilization: Laser and Punch, 2023 to 2025

3. Brake Hours: Setups, Standards and the Peak

Sections 1 and 2 established the press brakes as the shop's primary constraint and mapped how their queue time rises with load. This section is aimed at the brake hours themselves: where hours are lost to setups running over standard and how many can be recovered, whether the standard hours the schedule is planned in are right, and where crewed hours fall short. The next report, Discrete Event Simulation: On-time Delivery, takes these measured hours as its inputs.

Utilization is running machine hours over hours available, and the shop controls both sides: how many hours each job takes, and how many hours are crewed. Downtime (9 hours a week at 97% uptime) and run time over standard (9 hours a week at 1.05 of standard) are small. Setups over standard are not: 36 hours a week, which is 10.4 points of brake utilization against the standards the schedule plans with, and about 7.8 points once the small-lot standards are corrected.

Brake Utilization and Queue Time on the Curve, With and Without Setup Overrun, 2025
Brake Utilization and Queue Time on the Curve, With and Without Setup Overrun, 2025

Brake setups over standard

Setups over standard on the brakes ran 1,847 hours in 2025, with the median brake setup running at 1.16 of standard and the 90th percentile at 2.05. This overrun is unique to brakes: no other work center exceeds 51 setup hours over standard in the year or a median ratio of 1.00. See Appendix Table 12 for additional detail.

Four overlapping conditions drove most of the overrun. Setups handed over at a shift boundary are 13% of setups and 51% of the overrun. Lots under 25 pieces are 49% of setups and 67% of the overrun, because the setup standards under-plan small lots (median 1.28 against 1.05 on larger lots). First setups of a part by an operator run at 1.29 against 0.99 when the operator has set it up before. Enclosures and chassis run at 1.31 and 1.29 against 1.09 to 1.10 for panels and brackets. See Appendix Tables 13 to 17 for additional detail.

Share of Brake Setups Against Share of Overrun Hours by Condition, 2025
Share of Brake Setups Against Share of Overrun Hours by Condition, 2025

What can be recovered

Three changes recover 13.9 of the 36 hours a week, 4.1 points of brake utilization, taking the brakes from 91% to 87% and queue time on the curve from 2.34 to 1.46 days per operation. Running the top 12 part-operations by overrun at standard releases 8.1 hours a week; the rest of the overrun is spread across 1,943 part-operations. Assigning repeat setups to an operator who has set the part up before releases 4.3: first setups of a repeat part by a new operator ran at 1.58 of standard against 1.31 with prior familiarity. A handover standard, under which the operator who starts a setup finishes it or leaves a written handover at the machine, releases 1.5, the handover's own cost once long setups are set aside. The report Discrete Event Simulation: On-time Delivery carries these 13.9 hours as the setup program. See Appendix Tables 18 to 21 for additional detail.

Brake Hours a Week Released by Setup Lever, 2025
Brake Hours a Week Released by Setup Lever, 2025

Planning standards

The schedule and the quote are built in standard hours, and the brake standards understate what the brakes actually run: the 2025 plan carried 13,940 brake hours against 15,967 run, a gap of 2,027 hours, or 11.4 points of utilization. Two corrections bring part of it onto the plan. Raising the setup standard on lots under 25 pieces by 23% adds 483 hours. Refreshing the 525 stale brake standards (those dated at the part's first quote, which run 10% further above standard than refreshed parts) adds 242. Together they close 36% of the gap, and the setup recovery above takes a further 724 hours off the actual. What remains, 578 hours, is the overrun the plan will still not see. See Appendix Tables 22 to 25 for additional detail.

Brake Hours: Planned Against Actual, 2025
Brake Hours: Planned Against Actual, 2025

Away from the constraint, the L2 and L3 lasers run at 0.82 of their run standard, so planned laser hours are overstated by 12.9%; setting those standards to measured is an estimating correction (Flow and On-time Delivery, Section 4) rather than a capacity one.

Where crewed hours fall short

Setup recovery adds 13.9 brake hours a week; the year-end peak needs far more. In the six weeks from November 11, 2024 the shop released 361 brake standard hours a week against 284 of crewed capacity, a shortfall of about 77 hours a week that went into the queue. Queue-triggered Saturday shifts covered almost none of it: 2 shifts in six weeks, 28 hours in total. A Saturday brake shift as the shop has worked it supplies 6.8 machine hours, 8% of the weekly gap; one with both B1 and B2 crewed supplies about 15, 17%. Discrete Event Simulation: On-time Delivery tests one every week from November through February. See Appendix Table 26 for additional detail.

Brake Hours Released Against Capacity by Week, Q4 2024 to Q1 2025
Brake Hours Released Against Capacity by Week, Q4 2024 to Q1 2025

The robotic weld cell runs one shift at 82% utilization and is at or above 95% in 19 weeks of 52; its second shift is uncrewed. Enclosures are 78% of its hours, so a second shift would serve the enclosure customers first. The simulation report tests and prices crewing it. See Appendix Table 27 for additional detail.

Measured from the record: the brakes lose 36 hours a week to setups over standard, enough to put them above the knee of their curve on its own; 13.9 of those hours are recoverable by three changes; the small-lot setup standard, 546 stale standards and the L2 and L3 run standards misstate planned hours in known directions; the year-end peak releases about 77 brake hours a week more than the brakes can run; and the robotic weld cell's second shift is uncrewed. Discrete Event Simulation: On-time Delivery takes these as its inputs.

Appendix

Table 1. Utilization and machine uptime by work center

Work centerMachinesOperationsScheduled hoursMachine hoursDowntime hoursAvailable hoursUtilizationUptimeQueue time, meanUtilization, Q2-Q4Uptime, Q2-Q4Queue time, mean, Q2-Q4
Press brake55,56618,30816,16547017,83891%97%3.0690%97%1.48
Robotic weld14201,9921,583571,93582%97%2.8783%97%3.21
Laser34,33410,1527,3593299,82375%97%75%97%
Assembly26843,9842,6311003,88468%97%1.6366%97%1.53
Inspection and pack25,1293,9842,5741443,84067%96%0.6965%96%0.74
Grind and deburr25,5723,9842,5751153,86967%97%0.8866%97%0.89
Punch18151,9921,293491,94367%98%64%98%
Hardware22,1183,9842,547833,90165%98%0.8365%98%0.84
Manual weld61,53311,9527,56734611,60665%97%0.8762%97%0.76
Powder coat12,3282,0521,111531,99956%97%0.5054%98%0.43

Table 2. Weekly utilization at or above 95% by work center: weeks, queue time, jobs at the work center and share of hours

2025

Work centerUtilizationWeeks at or above 95%Of which full five-day weeksQueue time in those weeksQueue time in the other weeksJobs at the work center in those weeks, daily meanJobs at the work center in the other weeks, daily meanShare of machine hours in those weeks
Press brake91%16 of 52143.392.9072.762.833%
Robotic weld82%19 of 52144.112.257.74.342%
Laser75%4 of 5225.381.12113.447.18%
Assembly68%9 of 5283.501.1312.04.325%
Inspection and pack67%1 of 5211.100.6828.314.63%
Grind and deburr67%0 of 5200.8820.80%
Punch67%9 of 5282.070.7811.28.326%
Hardware65%0 of 5200.839.00%
Manual weld65%1 of 5210.660.8712.39.03%
Powder coat56%0 of 5200.5014.60%

2025 Q2-Q4

Work centerUtilizationWeeks at or above 95%Of which full five-day weeksQueue time in those weeksQueue time in the other weeksJobs at the work center in those weeks, daily meanJobs at the work center in the other weeks, daily meanShare of machine hours in those weeks
Press brake90%12 of 39101.911.2740.231.433%
Robotic weld83%16 of 39124.302.488.24.748%
Laser75%2 of 3911.480.8399.146.65%
Assembly66%4 of 3943.831.1214.74.316%
Grind and deburr66%0 of 3900.8921.20%
Inspection and pack65%1 of 3911.100.7328.315.34%
Hardware65%0 of 3900.849.10%
Punch64%5 of 3941.720.6110.58.020%
Manual weld62%0 of 3900.768.20%
Powder coat54%0 of 3900.4313.40%

2023 to 2025

Work centerWeeks at or above 95%Queue time in those weeksQueue time in the other weeks
Robotic weld39 of 1553.581.66
Press brake28 of 1552.571.45
Punch20 of 1552.560.50
Assembly18 of 1553.601.06
Laser11 of 1553.950.93
Manual weld7 of 1552.370.96
Grind and deburr1 of 1550.710.83
Hardware1 of 1551.930.82
Inspection and pack1 of 1551.100.70
Powder coat0 of 1550.48

Brake queue 90th percentile by quarter, 2025

Q1Q2Q3Q4
15.64.84.03.5

Table 3. Weekly queue time by utilization band and work center, full weeks 2023 to 2025

Work centerUtilization in the weekWeeksQueue time, mean of weeksMedian
Press brakebelow 80%460.330.28
Press brake80% to 85%120.810.38
Press brake85% to 90%151.771.02
Press brake90% to 95%422.121.16
Press brakeat or above 95%232.731.98
Robotic weldbelow 80%810.950.69
Robotic weld80% to 85%103.282.77
Robotic weld85% to 90%92.562.21
Robotic weld90% to 95%62.972.49
Robotic weldat or above 95%303.432.73
Laserbelow 80%1010.650.56
Laser80% to 85%131.020.95
Laser85% to 90%82.171.11
Laser90% to 95%81.511.01
Laserat or above 95%83.482.60
Assemblybelow 80%970.840.74
Assembly80% to 85%111.150.95
Assembly85% to 90%71.271.02
Assembly90% to 95%91.881.18
Assemblyat or above 95%142.952.89
Inspection and packbelow 80%1310.680.68
Inspection and pack80% to 85%20.800.80
Inspection and pack85% to 90%40.680.68
Inspection and packat or above 95%11.101.10
Grind and deburrbelow 80%1290.780.75
Grind and deburr80% to 85%50.790.78
Grind and deburr85% to 90%31.361.07
Grind and deburr90% to 95%10.850.85
Punchbelow 80%1050.250.09
Punch80% to 85%60.730.61
Punch85% to 90%60.830.73
Punch90% to 95%41.991.40
Punchat or above 95%172.271.55
Hardwarebelow 80%1250.770.76
Hardware80% to 85%100.950.84
Hardware85% to 90%20.810.81
Hardware90% to 95%11.111.11
Manual weldbelow 80%1090.720.66
Manual weld80% to 85%61.591.22
Manual weld85% to 90%60.900.92
Manual weld90% to 95%121.821.08
Manual weldat or above 95%52.261.13
Powder coatbelow 80%1370.470.40
Powder coat85% to 90%10.970.97

Weeks of 2025 at or above 80% and 95% utilization

Work centerWeeks at or above 80%Weeks at or above 95%Weeks in the year
Press brake461652
Robotic weld321952
Laser20452
Assembly21952
Inspection and pack7152
Grind and deburr5052
Punch18952
Hardware7052
Manual weld11152
Powder coat0052

Table 4. Fitted queue time curve by work center

Work centerMachines (m)Scale kR-squared, 13-weekRank correlationUtilization range fittedR-squared, single weeksQueue time at 75%At 85%At 90%At 92%
Laser31.7170.640.7953% to 89%0.111.352.844.726.14
Punch10.4550.550.8243% to 79%0.351.372.584.105.23
Press brake51.3990.450.8969% to 95%0.150.551.252.162.85
Robotic weld10.4150.270.7939% to 95%-0.321.242.353.734.77
Manual weld66.3620.190.6244% to 79%-0.841.934.537.9410.55
Powder coat10.455-0.160.3741% to 62%-0.201.362.584.095.23
Assembly21.337-0.330.8041% to 89%-0.121.763.525.747.41
Hardware21.220-14.830.2546% to 72%-11.641.613.215.246.76
Inspection and pack20.959-17.42-0.2147% to 73%-18.391.262.534.125.31
Grind and deburr21.058-18.950.4547% to 75%-8.251.392.794.545.86

Table 5. Position of each work center on its curve

Work centerUtilizationQueue time measuredQueue time on curveWeeks at or above 95%Utilization, Q2-Q4Queue time measured, Q2-Q4Queue time on curve, Q2-Q4Weeks at or above 95%, Q2-Q4
Press brake91%3.062.3416 of 5290%1.482.2112 of 39
Robotic weld82%2.871.8719 of 5283%3.201.9816 of 39
Laser75%1.391.354 of 5275%0.851.342 of 39
Assembly68%1.631.189 of 5266%1.531.094 of 39
Inspection and pack67%0.690.821 of 5265%0.740.751 of 39
Grind and deburr67%0.880.880 of 5266%0.890.850 of 39
Punch67%1.060.919 of 5264%0.790.825 of 39
Hardware65%0.830.950 of 5265%0.840.910 of 39
Manual weld65%0.870.941 of 5262%0.760.760 of 39
Powder coat56%0.500.570 of 5254%0.430.530 of 39

Table 6. Utilization and queue time for the five brakes and the robotic weld cell, 2025 and Q2-Q4

MachineCrewed shiftsUtilization, 2025Queue time, meanMedian90th percentileUtilization, Q2-Q4Queue time, mean, Q2-Q4Median, Q2-Q490th percentile, Q2-Q4
B1289.7%2.590.878.389.8%1.260.473.4
B2290.4%2.470.608.292.1%1.170.443.4
B3290.7%3.381.1810.189.6%1.740.724.9
B4291.7%3.191.079.790.1%1.500.524.2
B5190.7%3.481.1510.888.2%1.620.924.1
Robotic weld cell181.8%2.871.197.982.7%3.211.279.1

Table 7. The brakes and the robotic weld cell: hours and utilization on both bases

MachineWeekday scheduled hoursSaturday and extended hoursMachine hoursDowntime hoursUtilizationUtilization, weekday basisUptimeOperationsUtilization, Q2-Q4Weekday basis, Q2-Q4
B13,9841903,64711089.7%94.1%97%97589.8%91.8%
B23,9841903,67211190.4%94.8%97%94192.1%94.2%
B33,98403,52310090.7%90.7%97%1,46689.6%89.6%
B43,98403,55610791.7%91.7%97%1,35890.1%90.1%
B51,99201,7684390.7%90.7%98%82688.2%88.2%
Robotic weld cell1,99201,5835781.8%81.8%97%42082.7%82.7%

Table 8. Queue days by work center and driver of queue time, 2025

Work centerDriver of queue timeOperationsQueue daysShare
Press brakeLoad-driven5,56617,01344%
Laser (first operation)Load-driven4,3345,77115%
Grind and deburrSchedule-driven5,5724,90213%
Inspection and packSchedule-driven5,1293,5269%
HardwareSchedule-driven2,1181,7485%
Manual weldLoad-driven1,5331,3283%
Robotic weldLoad-driven4201,2073%
Powder coatSchedule-driven2,3281,1633%
AssemblyLoad-driven6841,1153%
Punch (first operation)Load-driven8158162%
All38,589100%

Table 9. Assembly: hot weeks, where its work comes from, and the weekly correlations

By year

YearUtilizationQueue timeWeeks at or above 95%Operations
2023*54%1.473 of 51541
202462%1.186 of 52579
202568%1.639 of 52684

* 2023 includes the first four weeks of the record, when jobs already in process raise the queue time; from the week of January 30 the 2023 queue time is 1.00 days per operation.

Weeks at or above 95% against the other weeks, 2025

Weeks at or above 95%Other weeks
Weeks943
Utilization99%61%
Queue time3.501.13
Arrivals a week14.212.7
Arrivals a week on jobs routed through the robotic weld cell2.32.3
Robotic weld cell share of arrivals16%18%
Machine hours per operation4.483.65

Where assembly's work comes from, 2025

Weld on the job's routingOperationsShare of assembly hoursQueue time90th percentile
No weld36657%1.865.0
Manual weld bays20029%1.403.1
Robotic weld cell11813%1.313.0
Operation before assemblyShare of assembly operations
Powder coat48%
Outside processing25%
Grind and deburr14%
Press brake8%
Hardware5%

Hours by part family, 2025

Part familyOperationsMachine hoursShare of hours
Assembly5232,07979%
Enclosure16153921%

Weekly correlations

Across the weeks of 2025Correlation
Assembly utilization and assembly queue0.62
Assembly utilization and arrivals in the week0.53
Assembly utilization and arrivals from robotic weld routings0.18
Assembly utilization and robotic weld cell hours, same week0.13
The same, robotic weld cell hours one week earlier0.01
The same, two weeks earlier-0.01

Table 10. Laser weeks, November and December 2024

Week startingWorking weekdaysLaser utilizationFirst operations startedFirst-operation queue time, mean90th percentile
2024-11-04575%820.722.2
2024-11-11597%612.125.1
2024-11-18595%1173.077.4
2024-11-25384%231.053.7
2024-12-02579%973.828.5
2024-12-09595%1114.1711.3
2024-12-16596%1066.1713.7

Table 11. The lasers: first-operation queue time and material wait by month, and the three machines

By month, 2025

Month of the first cutFirst operationsFirst-operation queue time, mean90th percentileMaterial wait, meanFirst operations with a material waitLaser utilization
January4765.6215.31.0337%81%
February3550.872.20.9838%76%
March3240.712.00.7933%68%
April3350.682.10.7033%69%
May3790.692.20.7234%78%
June3530.541.50.8332%65%
July3150.832.30.8337%69%
August3171.183.60.9134%81%
September3881.314.90.7828%78%
October4090.611.80.8035%73%
November3440.832.30.7635%80%
December1451.365.21.3741%83%
20254,1401.394.30.8535%
2025 Q2-Q42,9850.862.50.8234%

The three machines, 2025

LaserScheduled hoursMachine hoursShare of laser hoursUtilizationUptimeRun hoursRun standard hoursRun hours over standardShare of laser standard hours
L11,9921,68923%90%94%1,5571,5191.0320%
L23,9842,86739%74%97%2,4933,0210.8340%
L33,9842,80438%72%98%2,4392,9890.8240%
All9,9607,359100%6,4887,5290.86100%

Table 12. Setup against standard by work center

Work centerSetupsMedian ratioHours over standard ratio90th percentileSetup hoursStandard hoursOverrun hours
Press brake5,2491.161.442.055,9984,1511,847
Grind and deburr5,2021.001.051.421,0911,04051
Manual weld1,4211.001.051.4074871037
Laser4,0571.001.041.3384481133
Inspection and pack4,7671.001.041.4474771532
Powder coat2,1761.001.061.4057454430
Hardware1,9661.001.051.4051849227
Punch7611.001.041.4039738016
Robotic weld3921.001.031.4248647015
Assembly6481.001.041.392031948

Table 13. Brake setup against standard by period

PeriodSetupsMedian ratioHours over standard ratio90th percentileSetup hoursStandard hoursOverrun hours
20255,2491.161.442.055,9984,1511,847
2025 Q2-Q43,8231.181.452.054,3963,0271,369
2025 Q11,4261.121.422.051,6021,124478

Table 14. Brake setups handed over at a shift boundary, and by time left in the shift at the start

SetupSetupsMedian ratioHours over standard ratio90th percentileSetup hoursStandard hoursOverrun hoursShare of setupsShare of overrun
Not handed over4,5691.111.261.834,4783,56891087.0%49.3%
Handed over at a shift boundary6801.772.616.491,51958393713.0%50.7%
Afternoon (14:00 to 14:30)3041.692.536.406622624005.8%21.7%
Overnight (22:30 to 06:00)3061.712.667.307062664405.8%23.8%
Other702.252.754.0615155961.3%5.2%
Two-person setup, not handed over521.201.281.915543121.0%0.6%
Time left in the shift at setup startSetupsHanded overMedian ratioHours over standard ratio
Last 30 minutes31081.0%1.311.54
30 to 60 minutes32554.2%1.341.58
1 to 2 hours64317.1%1.131.46
2 to 4 hours1,3405.0%1.141.46
Over 4 hours2,6202.6%1.151.40

Table 15. Brake setups by lot-size band

Lot sizeSetupsMedian ratioHours over standard ratio90th percentileSetup hoursStandard hoursOverrun hoursMedian ratio, Q2-Q4
Under 252,5731.281.612.263,2572,0291,2281.30
25 to 992,0141.051.291.802,0591,6004591.06
100 and over6621.051.311.786825221601.07

Table 16. Brake setups by the operator's prior setups of the part

Prior setupsSetupsMedian ratioHours over standard ratio90th percentileSetup hoursStandard hoursOverrun hoursMedian ratio, Q2-Q4
None2,3611.291.582.242,9241,8551,0691.32
1 or 21,0170.991.301.811,0488092391.00
3 or more1,8711.101.361.902,0251,4875391.12

Table 17. Brake setups by part family

FamilySetupsMedian ratioHours over standard ratio90th percentileSetup hoursStandard hoursOverrun hoursMedian ratio, Q2-Q4
Assembly4751.111.362.125794271531.16
Bracket1,1021.091.351.809216802411.12
Chassis4851.291.622.367314522791.31
Enclosure1,0351.311.582.231,4929425501.30
Panel1,1901.101.351.921,1808763041.12
Weldment9621.141.412.091,0947733211.19

Table 18. The top 12 setup reduction candidates by overrun hours times work center utilization, 2025

PartOperationFamilySetupsMean lotSetup hoursStandard hoursMedian ratioOverrun hoursBrake hours a week at standard
P-10414620Panel19251251.3167.01.2684.31.62
P-10405040Enclosure16247197.6118.31.3079.41.53
P-10405020Enclosure15947187.8127.21.2760.61.16
P-10406220Chassis307873.234.51.6538.70.74
P-10408430Weldment9552124.289.30.9934.90.67
P-10416230Weldment793589.068.71.0220.20.39
P-10411130Weldment555366.747.91.2518.80.36
P-10442230Enclosure214445.627.11.3018.50.36
P-10413030Weldment424243.124.81.2418.40.35
P-10636530Bracket41519.42.67.4216.70.32
P-10429430Chassis213836.019.71.4516.30.31
P-10400630Weldment262835.820.81.3115.00.29

Table 19. Setup reduction candidates, top 20

Work centerPartOperationFamilySetupsMean lotSetup hoursStandard hoursMedian ratioOverrun hoursUtilizationScoreHours a week at standard
Press brakeP-10414620Panel19251251.3167.01.2684.391%76.41.62
Press brakeP-10405040Enclosure16247197.6118.31.3079.491%71.91.53
Press brakeP-10405020Enclosure15947187.8127.21.2760.691%54.91.16
Press brakeP-10406220Chassis307873.234.51.6538.791%35.10.74
Press brakeP-10408430Weldment9552124.289.30.9934.991%31.60.67
Press brakeP-10416230Weldment793589.068.71.0220.291%18.30.39
Press brakeP-10411130Weldment555366.747.91.2518.891%17.00.36
Press brakeP-10442230Enclosure214445.627.11.3018.591%16.70.36
Press brakeP-10413030Weldment424243.124.81.2418.491%16.60.35
Press brakeP-10636530Bracket41519.42.67.4216.791%15.20.32
Press brakeP-10429430Chassis213836.019.71.4516.391%14.80.31
Press brakeP-10400630Weldment262835.820.81.3115.091%13.60.29
Press brakeP-10420330Enclosure184832.418.21.5814.291%12.90.27
Press brakeP-10440130Chassis46517.53.84.7313.791%12.50.26
Press brakeP-10420360Enclosure204130.617.41.7013.291%11.90.25
Press brakeP-10476220Weldment113220.17.31.1112.891%11.60.25
Press brakeP-10810130Enclosure89819.27.51.4211.791%10.60.22
Press brakeP-10430930Assembly373051.140.01.1911.191%10.10.21
Press brakeP-12056820Chassis12011.60.912.3610.791%9.70.21
Press brakeP-10429440Chassis194025.615.21.4410.491%9.40.20

Table 20. First setups of repeat parts where another operator had set the part up

SetupsCountSetup hoursStandard hoursHours over standard ratioRatio of setups with prior familiarity, same lot band and familyBrake hours a week releasedShare of brake machine hours
First setups of a part by the operator, all brake setups2,3612,9241,8551.58
Of which repeat parts1,3721,6891,0681.581.315.51.8%
Another current brake operator had set the part up, any shift1,0791,3198341.581.314.31.4%
Another current brake operator on the same shift had set the part up7699265951.561.312.80.9%

Table 21. Brake hours released: the handover and the candidate list

EstimateBasisBrake hours a yearBrake hours a weekShare of brake machine hours
Handed-over setups at the median ratio of setups not handed overratio 1.11 on 680 setups87516.85.4%
Setups started in the last hour of a shift at the ratio of setups started earlierhours-weighted ratio 1.58 against 1.43 on 644 setups, 68% handed over791.50.5%
Top 12 setup reduction candidates at standard886 setups4228.12.6%

Table 22. Run actual against standard by work center and laser

Work centerOperationsRun hoursStandard run hoursActual over standardActual over standard, Q2-Q4
Laser4,3346,4887,5290.8620.863
Manual weld1,5336,6876,6521.0050.998
Assembly6842,4152,3841.0131.010
Hardware2,1182,0291,9991.0151.021
Punch8158988791.0221.016
Inspection and pack5,1291,8331,7561.0441.045
Grind and deburr5,5721,4911,4251.0471.053
Press brake5,56610,2039,7431.0471.051
Robotic weld4201,1011,0401.0591.052
Powder coat2,3285415051.0711.070
MachineOperationsRun hoursStandard run hoursActual over standard
Laser L18721,5571,5191.025
Laser L21,7522,4933,0210.825
Laser L31,7102,4392,9890.816

Table 23. Stale-standard parts against refreshed parts

Work centerOperations on stale-standard partsRun ratio, staleRun ratio, refreshedGapSetup ratio, staleSetup ratio, refreshed
Assembly2081.1300.964+17.2%1.0370.970
Grind and deburr1,3071.1551.012+14.1%0.9820.980
Hardware4601.0810.998+8.4%0.9960.976
Inspection and pack1,1841.0951.026+6.7%0.9780.969
Laser1,0250.9080.847+7.2%0.9580.980
Powder coat5031.1701.053+11.2%0.9900.985
Press brake1,2331.1271.023+10.1%1.3831.359
Punch1861.0681.013+5.4%0.9340.984
Robotic weld1661.1811.000+18.0%0.9470.974
Manual weld3061.0860.982+10.5%1.0020.971

Table 24. Planned operation hours with standards refreshed

Work centerPlanned hoursWith stale standards refreshedChange
Assembly2,4982,605+4.3%
Grind and deburr2,5052,554+1.9%
Hardware2,4872,524+1.5%
Inspection and pack2,4652,493+1.1%
Laser8,3308,453+1.5%
Powder coat1,0691,078+0.8%
Press brake13,94014,181+1.7%
Punch1,2801,283+0.2%
Robotic weld1,5211,574+3.5%
Manual weld7,3197,477+2.2%
LaserHoursChange
Planned laser hours, current standards8,330+0.0%
With L2 and L3 run standards set to measured7,258-12.9%
With stale parts refreshed8,453+1.5%
With both7,381-11.4%

Table 25. Standard hours per job with standards refreshed, by routing class

Routing classJobsJobs for stale-standard partsStandard hours per jobStale parts refreshed, all jobsStale parts refreshed, their jobsL2 and L3 set to measuredBoth
All5,2421,2518.28+1.9%+8.0%-2.5%-0.6%
Repeat part3,7788098.23+1.7%+8.0%-2.4%-0.7%
New part4441319.03+2.0%+7.7%-2.5%-0.5%
Outside processing1,0203118.15+2.5%+8.0%-2.8%-0.2%

Table 26. Brake standard hours released against crewed brake capacity, the six weeks from November 11, 2024

Week startingWorking weekdaysBrake standard hours releasedCrewed capacity net of downtime, standard hoursShortfallSaturday brake shiftsExtended hoursSaturday and extended machine hours
2024-11-1154593041551016
2024-11-18533430529000
2024-11-25324718561000
2024-12-025253298-45000
2024-12-0954203061141016
2024-12-165455306149000
A week, on average361284772 in all0 in all32 in all

Table 27. The robotic weld cell: weeks by utilization band, hours by part family, setup and run against standard

Weeks by utilization band, 2025

Utilization in the weekWeeksOf which full five-day weeksOperationsQueue time
below 80%20191441.20
80% to 85%33263.33
85% to 90%55583.20
90% to 95%55513.56
at or above 95%19141414.11

Hours by part family, 2025

Part familyOperationsMachine hoursShare of hoursQueue time
Enclosure3061,24078%2.80
Weldment571389%2.63
Chassis271036%3.61
Assembly18624%2.72
Panel4252%4.74
Bracket8191%4.21

Setup and run against standard, 2025

HoursStandard hoursHours over standard
Setup4864701.03
Run1,1011,0401.06